MahaRERA · the public record
SHIVDHAM
JUNCTION OF RAMAKRISHNA MISSION MARG · JOIN TRAK INFRA PRIVATE LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2025
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51800034122
Delivery and registration
When is the project declared for completion?
SHIVDHAM is registered with MahaRERA as P51800034122 and the promoter has declared completion for 31 Dec 2025.
31 Dec 2025
declared completion
9months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51800034122 |
| Registered on | 24 Mar 2022 |
| Promoter-declared completion | 31 Dec 2025 |
| Current status | Certificate Signed |
| Against today | about 9 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIVDHAM record 16 quarterly progress reports since registration.
16quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Join Trak Infra is the promoter of record on 29 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
29projects
registered with MahaRERA
2flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In SHIVDHAM, ₹38.27 Cr of a declared ₹44.60 Cr estimated project cost is reported as incurred, about 85.8%, as at the last certified filing with MahaRERA.
85.8%
₹38.27 Cr
of ₹44.60 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In SHIVDHAM, 6 of 15 homes filed with MahaRERA are recorded as sold or booked, about 40%, and 9 remain available.
40%sold
6 of 15 homes
₹70.76 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹51.18 Cr (about 72%) is recorded as collected and ₹19.58 Cr as receivable. The project registers 41 homes in total, while this sold/unsold inventory filing covers 15 of them.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 6 registered agreements, the effective carpet rate is ₹48,518/sqft, with eight in ten falling between ₹43,803 and ₹58,246 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.
| Floor | Unit | Carpet | Govt reckoner value |
|---|---|---|---|
| Floor 10 | 1004 | 835 sqft (77.6 sqm) | ₹2.83 Cr |
| Floor 11 | 1104 | 835 sqft (77.6 sqm) | ₹2.83 Cr |
| Floor 13 | 1301 | 837 sqft (77.8 sqm) | ₹2.84 Cr |
| Floor 14 | 1404 | 1,468 sqft (136.35 sqm) | ₹4.97 Cr |
| Floor 17 | 1701 | 1,066 sqft (99.05 sqm) | ₹3.61 Cr |
| Floor 17 | 1702 | 2,164 sqft (201.05 sqm) | ₹7.33 Cr |
| Floor 17 | 1703 | 1,468 sqft (136.35 sqm) | ₹4.97 Cr |
| Floor 7 | 702 | 2,077 sqft (192.93 sqm) | ₹7.04 Cr |
| Floor 7 | 703 | 835 sqft (77.6 sqm) | ₹2.83 Cr |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 18 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 6 homes carry one, and 9 of the 15 are recorded unsold.
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In SHIVDHAM, 0 of the 9 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23 and 41 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| SHIVDHAM | 1 | G+23 | 41 | - |
Unit mix on the filing: 41 residential.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at JUNCTION OF RAMAKRISHNA MISSION MARG, 16TH ROAD, Andheri, Mumbai Suburban, 400052. Per the filed land record, the plot is bounded to the north by MAIN AVENUE ROAD, to the south by 18 POINT 30 M W RAMKRISHNA MISSION ROAD, to the east by EXISITNG 12 POINT 30 16TH ROAD and to the west by 17TH ROAD. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Chhatrapati Shivaji Int'l Airport | 4 km |
| Bandra Kurla Complex (BKC) | 4 km |
| Andheri MIDC / SEEPZ | 7 km |
| Lower Parel / Worli business district | 9 km |
| Powai / Hiranandani business park | 9 km |
| Nariman Point / Fort | 17 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.