Mumbai/Project record

MahaRERA · the public record

EL SIGNORA

ADARSH NAGAR · PARAS BUILDERS (1985)

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Feb 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Feb 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005086

Delivery and registration

When is the project declared for completion?

EL SIGNORA is registered with MahaRERA as P51800005086 and the promoter has declared completion for 28 Feb 2023.

28 Feb 2023

declared completion

43months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005086
Registered on09 Aug 2017
Promoter-declared completion28 Feb 2023
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for EL SIGNORA record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 23 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Paras Builders (1985) is the promoter of record on 38 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

38projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for EL SIGNORA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.

BuildingWingsFloorsDeclared completion
SHIV SFURTI SRA CHS LTD REHAB BLDG NO 21G+2331 Mar 2021
EL SIGNORA SALE BLDG 31G+2530 Mar 2022

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for EL SIGNORA, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019892910/11/2021Prakash Vishram Bane vs Paras Builder (1985)order passed
CC00600000020976729/01/2022Mr. Shivanna M Shetty vs M/s Paras Builders (1985)order passed
CC00600000020972404/02/2022PARADIGM EVOLVERS LLP vs RONGOM TAGORE MUKERJIorder passed
CC00600000033383930/12/2022Mr Rongom Tagore Mukherji vs Paradigm Evolvers LLPorder passed
CC00600000037512612/04/2023Paras Builders 1985 vs Manoj Kumar Pandeyorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered28 Feb 2023The Developer is implementing the slum rehabilitation scheme by constructing 2 rehab buildings and one Sale building No. 3 (“EL Signora Project”). The completion of the scheme has

Location, Land & Connectivity

Located at ADARSH NAGAR, OFF NEW LINK ROAD, Andheri, Mumbai Suburban, 400102. Per the filed land record, the plot is bounded to the north by D P ROAD, to the south by CTS 35 PT, to the east by D P ROAD and to the west by CTS 31 AND 35 PT. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park8 km
Bandra Kurla Complex (BKC)10 km
Lower Parel / Worli business district16 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari West

Aksa Tower
possession by Sep 2026 · HFI Industries
GSA Grandeur
Past its declared completion date · possession by Oct 2026 · G S A Constructions
Lashkaria Pearl
possession by Nov 2026 · Lashkaria Housing & Infrastructure P
A H Avenue
possession by Dec 2026 · A.h. Constructions
KEY Tech Park
possession by Dec 2026 · M/s Keytech
Universal Garden- B Wing
possession by Dec 2026 · Pagarani Universal Infrastructure Pvt Lt

Major developers building in Jogeshwari West

Other RERA-registered projects in Mumbai Suburban

Elanza Commercial
possession by Dec 2027 · Acme Complex Pvt Ltd
Elegance Heights
possession by Dec 2029 · SGF Enterprises
Elegant Residency
possession by Dec 2026 · Elegant Builders AND Developers
Element 7 8
possession by Apr 2028 · Agastya Infra
Elenora
possession by Sep 2026 · Parinee VIR Bhuvan Redevelopment Private
Elevate 9
possession by Mar 2031 · Meru Realty LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026