MahaRERA · the public record
EVANA D-2
THANE · VIHANG INFRASTRUCTURE PVT LTD
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2029
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700034145
Delivery and registration
When is the project declared for completion?
EVANA D-2 is registered with MahaRERA as P51700034145 and the promoter has declared completion for 31 Dec 2029.
31 Dec 2029
declared completion
39months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700034145 |
| Registered on | 24 Mar 2022 |
| Promoter-declared completion | 31 Dec 2029 |
| Current status | Certificate Signed |
| Against today | 39 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for EVANA D-2 record 22 quarterly progress reports since registration.
22quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Vihang Infrastructure is the promoter of record on 16 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
16projects
registered with MahaRERA
0flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In EVANA D-2, ₹67.21 Cr of a declared ₹86.90 Cr estimated project cost is reported as incurred, about 77.3%, as at the last certified filing with MahaRERA.
77.3%
₹67.21 Cr
of ₹86.90 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In EVANA D-2, 268 of 326 homes filed with MahaRERA are recorded as sold or booked (265 with registered agreements and 3 booked), about 82%, and 58 remain available.
82%sold
268 of 326 homes
₹144.81 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹86.49 Cr (about 60%) is recorded as collected and ₹58.31 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 268 registered agreements, the effective carpet rate is ₹11,343/sqft, with eight in ten falling between ₹10,929 and ₹12,128 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, home by home
Read from MahaRERA on 18 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 271 homes carry one, and 55 of the 326 are recorded unsold. Since we started watching this ledger, 6 homes have moved out of the unsold list, most recently on 09 September 2026.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 3603 | 431 sqft | Rs 47.17 lakh typical, over Rs 46.16 lakh to Rs 54.01 lakh | 38 filed on this stack, floors 1–39 |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.
In EVANA D-2, every one of the 55 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+44 and 326 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Building No.7 Wing D-2 | 1 | G+44 | 326 | - |
Unit mix on the filing: 317 residential and 9 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Legal & Litigation
The promoter has declared 8 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Thane Civil Court | 1119 | 2012 | For Writtenstatement |
| Thane Civil Court | 698 | 2010 | Exhibit Hearing |
| Thane Civil Court | 699 | 2010 | Suit Withdrawn |
| Thane Civil Court | 342 | 2008 | Reply |
| Thane Civil Court | 88 | 2015 | Exhibit Hearing |
| Thane Civil Court | 2141 | 2012 | Exhibit Hearing |
| Revenue Minister | restoration application of revision against Order 2713P-K121-J4 | 2013 | Pending For Argument |
| Revenue Minister | Revision filing date 11/03/2016 | 2016 | Close For Order |
Location, Land & Connectivity
Located at THANE, GB CROSS ROAD THANE , Thane, Thane, 400615. Per the filed land record, the plot is bounded to the north by N 19 16 07, to the south by N 19 16 07, to the east by 1N 19 16 04 and to the west by 1N 191 16 07. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 14 km |
| Andheri MIDC / SEEPZ | 15 km |
| Chhatrapati Shivaji Int'l Airport | 19 km |
| Bandra Kurla Complex (BKC) | 20 km |
| Lower Parel / Worli business district | 29 km |
| Nariman Point / Fort | 36 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.