Everglades - I

Palghar · FALCON DWELLERS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007188

Delivery and registration

When is the project declared for completion?

Everglades - I is registered with MahaRERA as P51800007188 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

71months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007188
Registered on17 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 71 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Everglades - I record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Falcon Dwellers is the promoter of record on 86 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

86projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Everglades - I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Everglades - I1G+830 Oct 2020

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for Everglades - I, with orders passed in 4 of them.

4complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019782930/07/2021Rushda Aziz Hakim vs Falcon Dwellers Pvt. Ltd.order passed
CC00600000019783130/07/2021Atiya Aziz Hakim vs Falcon Dwellers Pvt. Ltd.order passed
CC00600000011092116/09/2019Rajeev Amrish Puri vs Falcon Dwellers Private Limitedorder passed
CC00600000012093616/09/2019Rajeev Amrish Puri vs Falcon Dwellers Private Limitedorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020a. minor finishing work including some work on lift is pending b. Water connection to UG tank is pending c. formalities of OC is pending

Location, Land & Connectivity

Located at Palghar, Palghar, 400053. Per the filed land record, the plot is bounded to the north by INTERNAL LAYOUT ROAD, to the south by RG, to the east by BUILDING NO 5 and to the west by S NO 65. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ2 km
Chhatrapati Shivaji Int'l Airport3 km
Powai / Hiranandani business park4 km
Bandra Kurla Complex (BKC)5 km
Lower Parel / Worli business district14 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Falcon Dwellers Private Limited is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Falcon Dwellers Private Limited

Falcon Dwellers Private Limited
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Andheri West

Royale
possession by Sep 2026 · Khoker Synergy Developers
Transcon Triumph Tower 3
possession by Sep 2026 · Transcon Triumph Phase 2 Private Limited
ARC ONE
possession by Dec 2026 · Chandra Gupta Estates Private Limited
MDM Maestro
possession by Dec 2026 · MDM Realty LLP
Platinum Grandeur
possession by Dec 2026 · Platinum Strategic Developers LLP
Vengurlekars Chaitra
possession by Dec 2026 · Vengurlekars Shreesai Builders And Devel

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Everglades - II
declared completion Feb 2021 · Falcon Dwellers Private Limited
Evershine Bliss
possession by Dec 2027 · Evershine Builders Private Limited
Express Enclave
declared completion Sep 2020 · MD Globus Realty PVT LTD
Express Tower CHS
possession by Feb 2028 · Kosmos Developers
Fairmont
possession by Dec 2026 · Trident Ozone LLP
Fatemid Avenue
declared completion Dec 2018 · Opal Builders PVT LTD

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026