MahaRERA · the public record
Future Crown
Naina · FUTURE INFRA
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Mar 2030
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52000080739
Delivery and registration
When is the project declared for completion?
Future Crown is registered with MahaRERA as P52000080739 and the promoter has declared completion for 31 Mar 2030.
31 Mar 2030
declared completion
42months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52000080739 |
| Registered on | 01 Jul 2025 |
| Promoter-declared completion | 31 Mar 2030 |
| Current status | Certificate Signed |
| Against today | 42 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Future Crown record 8 quarterly progress reports since registration.
8quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Future Infra is the promoter of record on 34 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
34projects
registered with MahaRERA
2flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Future Crown in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Future Crown | 1 | G+11 | - |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at Naina, TPS 1 NAINA, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by Final Plot No 20, to the south by 15 Meter Wide Road, to the east by Final Plot No 39 and to the west by Final Plot No 40A 20. These are the boundaries as recorded in the filed land record.