GALAXY APARTMENT

P99000011907 · promoter Arif Razak Memon

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP99000011907
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Arif Razak Memon is the promoter of record on 3 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
GALAXY APARTMENT WING A1G+3-
GALAXY APARTMENT WING B1G+3-
GALAXY APARTMENT WING C1G+3-

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250240515/07/2025ALLAN DBRITTO vs ARIF RAZAK MEMONorder passed
CC1250303228/08/2025ABRAR AKBAR SHAIKH vs ARIF RAZAK MEMONorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202130 Jun 2021The project was halted due to certain reasons beyond our control and then this year it was further affected due to corona pandemic. Now the work is in progress & the project will b

Location, Land & Connectivity

Located at Vasai, Palghar, 401501. Per the filed land record, the plot is bounded to the north by SURVEY NO 21, to the south by SURVEY NO 74 HISSA NO 2, to the east by SURVEY NO 74 HISSA NO 3 and to the west by SURVEY NO 74 HISSA NO 2. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~75 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ75 km
Powai / Hiranandani business park77 km
Chhatrapati Shivaji Int'l Airport79 km
Bandra Kurla Complex (BKC)82 km
Lower Parel / Worli business district89 km
Nariman Point / Fort97 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Ostwal Dream Land Phase - II
possession by Jul 2026 · Shree Ostwal Builders LTD
Parvati Homes
possession by Jul 2026 · Iconic Developers
Queens Villa
possession by Jul 2026 · Shashi Kuldeep Ostwal
Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises

Major developers building in Boisar

Other RERA-registered projects in Palghar

Galaxy Apartment
declared completion Dec 2025 · ACE Developers
Galaxy Avenue
declared completion May 2022 · Parshwanath Realtors
Galaxy Complex
possession by Jul 2026 · Ksquare Realty Private Limited
Galaxy Emperia Phase-1
declared completion Dec 2025 · Galaxy Shine Developers
Galaxy Emperia Phase-II
possession by Jun 2028 · Galaxy Shine Developers
Galaxy Garden - II
possession by Mar 2031 · Asian Builders And Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026