MahaRERA Property Intelligence · Thane

GAMI JADE

P51700034661 · VASHI · promoter Lal Gebi Infra

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP51700034661
Registered on20 Apr 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Lal Gebi Infra is the promoter of record on 10 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.

BuildingWingsFloorsDeclared completion
GAMI JADE1G+2531 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at VASHI, SECTOR 26, Thane, Thane, 400703. Per the filed land record, the plot is bounded to the north by 20 MTRS ROAD, to the south by PLOT NO 1, to the east by PLOT NO 1B and to the west by 20 MTR ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park12 km
Bandra Kurla Complex (BKC)15 km
Chhatrapati Shivaji Int'l Airport16 km
Andheri MIDC / SEEPZ16 km
Lower Parel / Worli business district22 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

LAL Gebi Infra Private Limited is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by LAL Gebi Infra Private Limited

LAL Gebi Infra Private Limited
FlaggedThane
LAL Gebi Infra Private Limited
FlaggedRaigarh
LAL Gebi Infra Private Limited
FlaggedRaigarh
LAL Gebi Infra Private Limited
FlaggedThane
LAL Gebi Infra Private Limited
FlaggedThane

Other RERA-registered projects in Vashi

Goodwill Bizhub
possession by Sep 2026 · M/s. Goodwill Dwellings LLP
Aurous
possession by Dec 2026 · Asaya Builders AND Developers LLP
Cyber Works
possession by Dec 2026 · Greenscape Ventures
Akshar Panchratna
possession by Jun 2027 · Akshar Dream Homes
Centonic
possession by Jun 2027 · Metro Lifescapes India LLP
Aykon
possession by Dec 2027 · Metro Lifescapes India LLP

Major developers building in Vashi

Other RERA-registered projects in Thane

Gami Reagan
declared completion Dec 2023 · Shri Gami Infotech PVT LTD
Gami Satyam Business Avenue
possession by Dec 2027 · Satyam Ventures Private Limited
Gami Satyam Skyscape
possession by Dec 2030 · Gami And Satyam Ventures Private Limited
Gami Solitaire
declared completion Dec 2024 · Anil Laxman Gami
Gami Telon
possession by Dec 2029 · LAL Gebi Infra Private Limited
Gami Terra
possession by Dec 2026 · LAL Gebi Infra Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026