Mumbai/Project record

MahaRERA · the public record

Gandharva

boisar · Wisdom Infrastructures

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000008614

Delivery and registration

When is the project declared for completion?

Gandharva is registered with MahaRERA as P99000008614 and the promoter has declared completion for 30 Mar 2023.

30 Mar 2023

declared completion

42months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000008614
Registered on19 Aug 2017
Promoter-declared completion30 Mar 2023
Current statusCertificate Signed
Against todayabout 42 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Gandharva record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 23 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Gandharva in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Gandharva Building No 11--
Gandharva Building No 21--
Gandharva Building No 31-28 Feb 2021
Gandharva Building No 41G+328 Feb 2021
Gandharva Building No 51G+328 Feb 2021
Gandharva Building No 61G+328 Feb 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Aug 2020AMENDEMENT TO CC , AND PURCHASE OF TDR, MAJOR CHANGES IN STRUCTURE NEEDED EXTENTION OF PROJECT REGISTRATION TO COMPLETE THE SAME
30 Aug 202030 Sep 2022COVID-19 AFFECTED PROJECT IN BAD WAY, NON AVAILABILITY OF LABOUR FORCES AND NON AVAILABILITY OF MATERIAL ON TIME AT SITE LEAD US TO EXTEND THE PROJECT WITH PRIOR APPROVAL OF ALLOTT

Location, Land & Connectivity

Located at boisar, BOIsar, Vasai, Palghar, 401504. Per the filed land record, the plot is bounded to the north by S No 11, to the south by Village Road, to the east by Petrol Pump S no 11 and to the west by S No 11. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~78 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ78 km
Powai / Hiranandani business park80 km
Chhatrapati Shivaji Int'l Airport83 km
Bandra Kurla Complex (BKC)85 km
Lower Parel / Worli business district92 km
Nariman Point / Fort100 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pasthal

Mahavir Business Centre
possession by Dec 2026 · Rajesh Developers
Balaji Complex Phase-2
possession by Dec 2027 · B R Housing
Mahavir Neytra
possession by Dec 2027 · Rajesh Construction
Mahavir Vihar Building NO 4 Type E
possession by Dec 2027 · Rajesh Construction
Shree Samarth Apartment
Not filing quarterly progress reports · possession by Dec 2027 · Aakash Keshmani Singh
Ramsetu
possession by Aug 2029 · Satvik Builders & Developers

Other RERA-registered projects in Palghar

Gandhi Industrial Park
declared completion Jan 2026 · Gandhi Builders PVT LTD
Ganesh Apartment
declared completion Mar 2024 · Tarkeshwar Hariprasad RAI
Ganesh Apartment
declared completion Jan 2022 · Vishnu Govind Patil
Ganesh Darshan Building -1 Type -A
possession by Dec 2028 · Dwarkesh Developers
Ganga CO OP HSG LTD
declared completion May 2026 · Viva Rium Builders & Developers
Gangotri Heights
possession by Dec 2028 · Shree Yogi Builders & Developer

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026