Mumbai/Project record

MahaRERA · the public record

GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2

NALLASOPARA WEST · SHIVANI ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 May 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000046065

Delivery and registration

When is the project declared for completion?

GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 is registered with MahaRERA as P99000046065 and the promoter has declared completion for 31 May 2027.

31 May 2027

declared completion

8months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000046065
Registered on15 Jun 2022
Promoter-declared completion31 May 2027
Current statusCertificate Signed
Against today8 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Shivani Enterprises is the promoter of record on 4 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GEMINI CO-OP HOUSING SOCIETY LTD PHASE 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
GEMINI CO-OP HOUSING SOCIETY LTD PHASE 21G+1031 May 2027

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NALLASOPARA WEST, SOPARA VILLAGE , Vasai, Palghar, 401203. Per the filed land record, the plot is bounded to the north by INTERNAL ROAD, to the south by PLOT NO 12, to the east by 20 M DP ROAD and to the west by LAYOUT RG. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shivani Enterprises is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shivani Enterprises

Shivani Enterprises
Past its declared completion datePalghar

Other RERA-registered projects in Nallasopara West

Kaneri Heights
possession by Sep 2026 · Shekhar Bhoir AND Others
Kunal Height
possession by Dec 2026 · Shree SAI Builders & Developers
Vimal Classic
possession by Dec 2026 · OM Vimal Developers
Anant Tower E AND F
possession by Dec 2026 · Shantinath Enterprises
Dhananjay Avenue
possession by Dec 2026 · SAI Kiran Builder AND Developers
Sai Baba Nagar Residential With Shopline Building With A B C Wings
Not filing quarterly progress reports · possession by Dec 2026 · Shreeji Associates

Other RERA-registered projects in Palghar

Gemini CO-Operative Housing Society LTD
declared completion Dec 2022 · Shivani Enterprises
Genisia Pinnacle
possession by Jun 2029 · Genisia Realty
Gharkul
declared completion Aug 2026 · Achole Infra LLP
Ghodela 27 Park View
possession by Dec 2026 · Ghodela Properties
Ghodela 27 Park View Phase 2
possession by Dec 2030 · Subhash Construction
Girdhari Heights
declared completion Apr 2026 · Shree Krishna Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026