MahaRERA Property Intelligence · Raigarh

GOLD VALLEY KONKAN

P52000005331 · promoter Goka Engineering Co

Certificate SignedDue 31 Dec 2017

Delivery & Registration

MahaRERA registrationP52000005331
Registered on11 Aug 2017
Promoter-declared completion31 Dec 2017
Current statusCertificate Signed
Against todayabout 103 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Goka Engineering Co is the promoter of record on 26 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
SECTOR A2- A11G+1-
GVK A2-A21G+1-
GVK A2- D1G+1-
GVK A2-C11G+1-
GVK A2-C21G+1-
GVK A2-B1G+1-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000008956102/06/2019DEEPA PRADHAN vs GOKA ENGINEERING COMPANY PVT LTD, DIRECTORS PRAKASH KANE, AMOL KANEorder passed

Location, Land & Connectivity

Located at Pune City, Pune, 401403. Per the filed land record, the plot is bounded to the north by PLOT NO 136, to the south by ROAD, to the east by PLOT NO 148 and to the west by SNO 80. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~89 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort83 km
Lower Parel / Worli business district89 km
Bandra Kurla Complex (BKC)92 km
Chhatrapati Shivaji Int'l Airport94 km
Powai / Hiranandani business park95 km
Andheri MIDC / SEEPZ98 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Goka Engineering CO PVT LTD is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Goka Engineering CO PVT LTD

Goka Engineering CO PVT LTD
FlaggedRaigarh

Other RERA-registered projects in Manor

15 Manor - Belvedere 2
possession by Dec 2026 · RV Infra
Myzo Suites
possession by Dec 2027 · Myzo Infra Private Limited
Myzo Suites Building NO 3 - A Wing
Not filing quarterly progress reports · possession by Dec 2027 · Ayush Reality
Godrej Country Estate
declared completion Apr 2026 · Godrej Projects Development Limited
Bandhan Heritage Phase II
Not filing quarterly progress reports · declared completion Dec 2025 · Mahi Links
Riddhi Siddhi Park Phase-2
Past its declared completion date · declared completion Jun 2024 · Riddhi Siddhi Builders

Other RERA-registered projects in Raigarh

Gold Valley Konkan Bungalows Phase 1
declared completion Dec 2025 · Goka Engineering CO PVT LTD
Gold Valley Konkan Sect C
declared completion Mar 2022 · Goka Engineering Company PVT LTD
Golden Arambh
declared completion Jun 2023 · Golden Stone Construction
Golden Corniche
possession by Dec 2028 · Golden Reality
Golden Heights
declared completion Oct 2020 · Golden Height
Golden Palms
possession by Dec 2029 · Akshay Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026