Mumbai/Project record

MahaRERA · the public record

GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED

GOREGOAN WEST · DILIP DOSHI

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800028730

Delivery and registration

When is the project declared for completion?

GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED is registered with MahaRERA as P51800028730 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800028730
Registered on25 Mar 2021
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Dilip Doshi is the promoter of record on 135 projects registered with MahaRERA, 26 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

135projects

registered with MahaRERA

26flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED1G+2431 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at GOREGOAN WEST, SIDDHARTH NAGAR ROAD, Borivali, Mumbai Suburban, 400104. Per the filed land record, the plot is bounded to the north by KAUSTUBH CHS, to the south by VIVEK COLLEGE, to the east by BUILDING NO 16 and to the west by BUILDING NO 23. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ20 km
Chhatrapati Shivaji Int'l Airport24 km
Bandra Kurla Complex (BKC)25 km
Lower Parel / Worli business district34 km
Nariman Point / Fort41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon West

Hitendra Dhamm Shabha Co-Operative Housing Society Limited
possession by Sep 2026 · Crystal Construction Company
Sahakar Revanta
possession by Sep 2026 · Sahakar Builders & Developers
Vallabh Krupa Chsl
possession by Oct 2026 · Gun Rajan Constructions
Siddharth Nagar Gulmohar CHS LTD
possession by Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Paschim Jagruti CHS LTD
possession by Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Swami Vivekanand Chsl
possession by Dec 2026 · Dhariwal Developers Private Limited

Major developers building in Goregaon West

Other RERA-registered projects in Mumbai Suburban

Goregaon Vihar Darshan CHS LTD
declared completion Aug 2026 · Silver Lifespaces Private Limited
Govind Dham
possession by Mar 2031 · Ambrosial Developers Private Limited
Govind Prakash SRA CHS LTD
declared completion Dec 2018 · Om Sai Developers
Govind Prakash SRA CHS LTD
possession by Dec 2026 · Omsai Developers
Govind Solitaire
declared completion Jun 2026 · Shankh Developers Limited Liability Part
Govind Vishram CHS LTD
declared completion Dec 2024 · Konark Land Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026