Mumbai/Project record

MahaRERA · the public record

Govardhan Kunj

Post Hamrapur · Bhakti Nilayam Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

0units filed as unsoldInventory · 19 September 2026
01 May 2027declared completionMahaRERA registration · read 12 Jul 2026
80registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 May 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000051299

Delivery and registration

When is the project declared for completion?

Govardhan Kunj is registered with MahaRERA as P99000051299 and the promoter has declared completion for 01 May 2027.

01 May 2027

declared completion

8months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000051299
Registered on08 Jun 2023
Promoter-declared completion01 May 2027
Current statusCertificate Signed
Against today8 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Govardhan Kunj record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Bhakti Nilayam is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Govardhan Kunj, ₹30.58 Cr of a declared ₹31.08 Cr estimated project cost is reported as incurred, about 98.4%, as at the last certified filing with MahaRERA.

98.4%

₹30.58 Cr

of ₹31.08 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Govardhan Kunj, 80 of 80 homes filed with MahaRERA are recorded as sold or booked (48 with registered agreements and 32 booked), about 100%, and 0 remain available.

100%sold

80 of 80 homes

₹43.06 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹39.82 Cr (about 92%) is recorded as collected and ₹3.33 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 80 registered agreements, the effective carpet rate is ₹7,013/sqft, with eight in ten falling between ₹3,816 and ₹7,949 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 80 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

Every home in Govardhan Kunj is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 80 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 80 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3 and 80 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building No 7 Type D1G+364-
Building No 8 Type D1G+34-
Building No 9 Type D1G+34-
Building No 10 Type E1G+34-
Building no 11 Type F1G+34-

Unit mix on the filing: 80 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Post Hamrapur, Palghar, Vada, Palghar, 421303. Per the filed land record, the plot is bounded to the north by Gat no 274 275 276 and 296, to the south by Gat No 273 Part land, to the east by Gat No 266 271 and 272 and to the west by Hamrapur to Gorhe Village Road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vada

Rajeshree Plaza
possession by Nov 2026 · Liva Infra Builders And Developers
Balkrushna Sankul
Not filing quarterly progress reports · possession by Dec 2026 · Sai Construction
Navkar Hills Garden View Part-1
possession by Dec 2026 · Pyramid Properties
Navkar Hills River Bay View-Part-1
possession by Dec 2026 · Navkar Holiday Homes & Water Park LL
Navkar Hills Sunrise View-Part-1
possession by Dec 2026 · Navkar Holiday Homes & Water Park LL
Navkar Hills Sunset View Part-1
possession by Dec 2026 · Navkar Holiday Homes & Water Park LL

Other RERA-registered projects in Palghar

Govardhan Kunj
possession by Jan 2031 · Bhakti Nilayam Private Limited
Govind Enclave
declared completion Aug 2026 · M/s Divekar And Patil Construction
Govind Heights
declared completion Nov 2020 · Mani Govind Construction
Govind Heritage
possession by Dec 2027 · Babaji Construction CO.
Govind Tower
possession by Dec 2028 · Govind Constructions
Govinda Park
declared completion Apr 2020 · Govinda Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026