Mumbai/Project record

MahaRERA · the public record

GOVIND DHAM

AIROLI · YASH VIKRANT RAIKAR

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Aug 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Aug 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700021880

Delivery and registration

When is the project declared for completion?

GOVIND DHAM is registered with MahaRERA as P51700021880 and the promoter has declared completion for 28 Aug 2022.

28 Aug 2022

declared completion

49months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700021880
Registered on08 Aug 2019
Promoter-declared completion28 Aug 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GOVIND DHAM record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Yash Vikrant Raikar is the promoter of record on 17 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

17projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GOVIND DHAM in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
GOVIND DHAM1G+531 Aug 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at AIROLI, PLOT NO A 33 SECTOR 9A AIROLI, Kurla, Mumbai Suburban, 400708. Per the filed land record, the plot is bounded to the north by 6 MTR ROAD, to the south by PLOT NO A 32, to the east by PLOT NO A 34 and to the west by 6 MTR ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Yash Vikrant Raikar is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Airoli

Alliaance Galaxy
possession by Oct 2026 · Aashutosh Enterprise
Bramharaj Orchid
possession by Dec 2026 · Bramharaj Developers
ONE Pyramid
possession by Dec 2026 · Pacific Properties
Surbhi Sangeeta Co-Op. Housing Society Ltd
possession by Dec 2026 · Kumar & Kumar Builders LLP
Delta Luxuria
possession by Apr 2027 · Shreenathji Organisers PVT LTD
Delta Icon
possession by Jul 2027 · Shreenathji Organisers PVT LTD

Other RERA-registered projects in Thane

Govind Heights
possession by Dec 2027 · OM Construction
Govind Nilay CO. OP. Hou. SO. LTD
declared completion Feb 2025 · Sachin Dattatrya Gorle
Govindagraj Gruha
declared completion Dec 2020 · THE Square Feet Developers
Grace Square D1 And D2
possession by Dec 2029 · Skyline Infra
Grace Square Type D3
possession by Dec 2026 · Shree Sumatinath Enterprises LLP
Grace Square Type D4
declared completion Dec 2024 · Shree Sumatinath Enterprises LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026