MahaRERA Property Intelligence · Thane

GOVIND DHAM

P51700021880 · AIROLI · promoter Yash Vikrant Raikar

Certificate SignedDue 28 Aug 2022

Delivery & Registration

MahaRERA registrationP51700021880
Registered on08 Aug 2019
Promoter-declared completion28 Aug 2022
Current statusCertificate Signed
Against todayabout 47 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Yash Vikrant Raikar is the promoter of record on 15 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
GOVIND DHAM1G+531 Aug 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at AIROLI, PLOT NO A 33 SECTOR 9A AIROLI, Kurla, Mumbai Suburban, 400708. Per the filed land record, the plot is bounded to the north by 6 MTR ROAD, to the south by PLOT NO A 32, to the east by PLOT NO A 34 and to the west by 6 MTR ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Yash Vikrant Raikar is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Yash Vikrant Raikar

Yash Vikrant Raikar
FlaggedRaigarh

Other RERA-registered projects in Airoli

Shivesh Emerald
possession by Jul 2026 · Shivesh Realty Private Limited
Alliaance Galaxy
possession by Oct 2026 · Aashutosh Enterprise
Bramharaj Orchid
possession by Dec 2026 · Bramharaj Developers
ONE Pyramid
possession by Dec 2026 · Pacific Properties
Surbhi Sangeeta Co-Op. Housing Society Ltd
possession by Dec 2026 · Kumar & Kumar Builders LLP
Delta Luxuria
possession by Apr 2027 · Shreenathji Organisers PVT LTD

Major developers building in Airoli

Other RERA-registered projects in Thane

Govind Heights
declared completion Dec 2024 · Shivam Construction
Govind Heights
possession by Dec 2027 · OM Construction
Govind Nilay CO. OP. Hou. SO. LTD
declared completion Feb 2025 · Sachin Dattatrya Gorle
GR Galaxy
declared completion Jun 2023 · Shahzadali Abdulwaheb Chaudhary
Grace Square D1 And D2
possession by Dec 2029 · Skyline Infra
Grace Square Type D3
possession by Dec 2026 · Shree Sumatinath Enterprises LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026