Mumbai/Project record

MahaRERA · the public record

GREEN VALLEY PHASE 1

Mumbai Suburban · DHARTI INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000004664

Delivery and registration

When is the project declared for completion?

GREEN VALLEY PHASE 1 is registered with MahaRERA as P99000004664 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000004664
Registered on09 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GREEN VALLEY PHASE 1 record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Dharti Infra is the promoter of record on 23 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

23projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GREEN VALLEY PHASE 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
BUNGALOW NO 20 21 221G+1-
BUNGALOW N0 91G+1-
BUNGALOW NO 101G+1-
BUNGALOW 111G+1-
BUNGALOW 121G+1-
BUNGALOW NO 191G+1-
BUNGALOW 231G+1-
BUNGALOW 241G+1-
BUNGALOW 251G+1-
BUNGALOW 261G+1-
BUNGALOW 271G+1-
BUNGALOW 281G+1-
BUNGALOW 291G+1-
BUNGALOW 301G+1-
BUNGALOW 311G+1-
BUNGALOW 321G+1-
BUNGALOW NO 21G+101 Aug 2020
BUNGALOW NO 61G+101 Aug 2020
BUNGALOW NO 91G+101 Aug 2020
BUNGALOW NO 131G+101 Aug 2020
BUNGALOW NO 151G+101 Aug 2020
BUNGALOW NO 11G+001 Aug 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 20221 COVID PENDEMIC 2 UNAVAILABILITY OF LABOURS 3 SHORTAGE OF MATERIALS

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 441902. Per the filed land record, the plot is bounded to the north by RIVER, to the south by G NO 71, to the east by G NO 82 and to the west by G NO 86. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~819 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park819 km
Andheri MIDC / SEEPZ822 km
Chhatrapati Shivaji Int'l Airport824 km
Bandra Kurla Complex (BKC)824 km
Lower Parel / Worli business district831 km
Nariman Point / Fort834 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Dharti Infra is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Dharti Infra

Other RERA-registered projects in Wada

Green Valley Phase 2
possession by Dec 2028 · Dharti Infra

Other RERA-registered projects in Palghar

Green Valley Phase 2
possession by Dec 2028 · Dharti Infra
Green View Apartment
possession by Dec 2026 · Delight Developers
Greenpark-Orchid
declared completion Oct 2023 · Relstruct Buildcon Limited
Greenpark-Rose
declared completion Dec 2020 · Relstruct Buildcon Limited
Greenway
declared completion Dec 2019 · Greenway Properties
Guardwel Swastik Horizon
declared completion Sep 2024 · Swastik Spaces Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026