30 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000017713

Delivery and registration

When is the project declared for completion?

GREENPARK-ROSE is registered with MahaRERA as P99000017713 and the promoter has declared completion for 30 Dec 2020.

30 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000017713
Registered on06 Sep 2018
Promoter-declared completion30 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GREENPARK-ROSE record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Relstruct Buildcon Limited is the promoter of record on 3 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GREENPARK-ROSE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
BUILDING NO 11G+330 Jun 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BOISAR WEST, BOISAR TARAPUR ROAD, Borivali, Mumbai Suburban, 401502. Per the filed land record, the plot is bounded to the north by ADJ DHAHISAR CHI SHIV, to the south by 12 M WIDE ROAD, to the east by 9 M WIDE ROAD and to the west by PLOT NO 7. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Relstruct Buildcon Limited is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Relstruct Buildcon Limited

Relstruct Buildcon Limited
Past its declared completion datePalghar

Other RERA-registered projects in Kurgaon

Nisarg -Building No.2
possession by Dec 2026 · Agora Life Space
Solitaire Height
possession by Dec 2026 · Affak Arif Motiwala
Whitehill Residential
possession by Dec 2026 · Riva Realtors
Bhakti Avenue
possession by Mar 2027 · Bhakti Green Realty LLP
Aster Hans Heritage
possession by Sep 2028 · Hans Realtors
Emerald Woods 2
possession by Dec 2029 · Shrehit Developers

Other RERA-registered projects in Palghar

Greenway
declared completion Dec 2019 · Greenway Properties
Guardwel Swastik Horizon
declared completion Sep 2024 · Swastik Spaces Limited
Gulmohar Avenue
declared completion Apr 2025 · Himanshu Sham Tendulkar
Gulmohar Heritage Building NO 3 Wing C AND D
declared completion May 2019 · Viva Swastik Homes
Gulmohar Heritage Building NO 3 Wing E Phase I
declared completion Jun 2026 · Viva Swastik Homes
Gulmohar Heritage Building No 3 Wing E Phase Ll
possession by Dec 2026 · Viva Swastik Homes

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.