GULMOHAR HERITAGE BUILDING NO 3 WING C AND D

Nallasopara West · VIVA SWASTIK HOMES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 May 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000002070

Delivery and registration

When is the project declared for completion?

GULMOHAR HERITAGE BUILDING NO 3 WING C AND D is registered with MahaRERA as P99000002070 and the promoter has declared completion for 31 May 2019.

31 May 2019

declared completion

88months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000002070
Registered on31 Jul 2017
Promoter-declared completion31 May 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GULMOHAR HERITAGE BUILDING NO 3 WING C AND D record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Viva Swastik Homes is the promoter of record on 134 projects registered with MahaRERA, 18 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

134projects

registered with MahaRERA

18flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GULMOHAR HERITAGE BUILDING NO 3 WING C AND D in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
GULMOHAR HERITAGE BUILDING NO 3 WING C1G+15-
GULMOHAR HERITAGE BUILDING NO 3 WING D1G+15-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 May 2019Respected Sir/Maam, We M/S Viva Swastik Homes, promoter of project "Gulmohar Heritage Building No.3. Wing C&D" have completed our project in july 2017. We have applied for Consen
31 May 201931 May 2019we have received Consent To Operate order on dated - 31/05/2018. Now, we have applied for Occupancy Certificate for the above project to vasai virar city municipal corporation [vvc

Location, Land & Connectivity

Located at Nallasopara West, Vasai, Palghar, 401203. Per the filed land record, the plot is bounded to the north by SURVEY NO 272 , to the south by GULMOHAR HERITAGE BUILDING NO 3 WING E, to the east by GARDEN and to the west by 18 MTR D P ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ34 km
Powai / Hiranandani business park36 km
Chhatrapati Shivaji Int'l Airport38 km
Bandra Kurla Complex (BKC)41 km
Lower Parel / Worli business district48 km
Nariman Point / Fort56 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Viva Swastik Homes is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Viva Swastik Homes

Viva Swastik Homes
FlaggedPalghar
Viva Swastik Homes
FlaggedPalghar
Viva Swastik Homes
FlaggedPalghar

Other RERA-registered projects in Nallasopara West

Kaneri Heights
possession by Sep 2026 · Shekhar Bhoir AND Others
Kunal Height
possession by Dec 2026 · Shree SAI Builders & Developers
Vimal Classic
possession by Dec 2026 · OM Vimal Developers
Anant Tower E AND F
possession by Dec 2026 · Shantinath Enterprises
Dhananjay Avenue
possession by Dec 2026 · SAI Kiran Builder AND Developers
Sai Baba Nagar Residential With Shopline Building With A B C Wings
Not filing quarterly progress reports · possession by Dec 2026 · Shreeji Associates

Other RERA-registered projects in Palghar

Gulmohar Heritage Building NO 3 Wing E Phase I
declared completion Jun 2026 · Viva Swastik Homes
Gulmohar Heritage Building No 3 Wing E Phase Ll
possession by Dec 2026 · Viva Swastik Homes
Gurmukh Apartments By Amrit Developers
possession by Dec 2028 · Divekar AND Vanmali Constructions
Guru Darshan Chsl
possession by Dec 2028 · Shree Mahavir Builders AND Developers
Guru Govind Singh Nagar CHS LTD
possession by Dec 2030 · OM SAI Developers
Guruji Residency
declared completion Dec 2023 · Navkar Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.