Mumbai/Project record

MahaRERA · the public record

Grove Towers

Mumbai City · Ornate Spaces Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Nov 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Nov 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900009142

Delivery and registration

When is the project declared for completion?

Grove Towers is registered with MahaRERA as P51900009142 and the promoter has declared completion for 29 Nov 2024.

29 Nov 2024

declared completion

22months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900009142
Registered on19 Aug 2017
Promoter-declared completion29 Nov 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Grove Towers record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ornate Spaces is the promoter of record on 13 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

13projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Grove Towers in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+47.

BuildingWingsFloorsDeclared completion
Tower 11G+3930 Nov 2023
Tower 21G+4730 Nov 2023

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for Grove Towers, with orders passed in 3 of them.

4complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019218414/01/2020UTI EMPLOYEE SAI SAMRUDDHI CO-OPERATIVE HOUSING SOCIETY LTD (society) vs ORNATE SPACES PRIVATE LIMITEDorder passed
CC00600000014113503/10/2019PNB Housing Finance Limited vs Ornate Spaces Private Limitedorder passed
CC00600000019407818/09/2020Aarif Ahsan Khan vs Ornate Spaces Pvt. Ltdpending / no order on file
CC00600000019908719/11/2021Mr Mohammed Aarif Khan vs Ornate Spaces Pvt Ltdorder passed

A co-operative housing society is recorded as the complainant (UTI EMPLOYEE SAI SAMRUDDHI CO-OPERATIVE HOUSING SOCIETY LTD), and MahaRERA has passed an order.

Location, Land & Connectivity

Located at Ward FNorth, Mumbai City, 400014. Per the filed land record, the plot is bounded to the north by CTS 2A part 2B part Oshiwara Police station, to the south by DP Road, to the east by CTS no 9 part and to the west by DP Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district2 km
Bandra Kurla Complex (BKC)6 km
Chhatrapati Shivaji Int'l Airport9 km
Nariman Point / Fort10 km
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar East

Anchor Sky D
Deregistered by MahaRERA · possession by Dec 2026 · Om Shanti Housing Development Company
Yash Supriya
possession by Dec 2026 · Yash Construction Company
Nine Reflex
possession by Dec 2026 · Reflex Projects LLP
Chirag Heights
possession by Dec 2026 · Nettheim Builders LLP
EL Mejor
possession by Dec 2026 · Arth Realtech Spaces PVT LTD
Panchratna-NX
possession by Dec 2026 · Sudhir Kishor Desai

Other RERA-registered projects in Mumbai City

GSA Grandeur
possession by Oct 2026 · G S A Constructions
Gulab Mansion
possession by Aug 2027 · Jyotindrakumar Punamchand Shah
Gulmohar Terrace
possession by Dec 2027 · Shining SUN Constructions
Gundecha-KBK-Magnum Phase I
possession by Mar 2027 · Gundechaconstructionpvtltd
Gurukrupa Alaknanda
possession by Dec 2026 · Gurukrupa Realcon Infrastructure Develop
Gurukrupa Building
possession by Mar 2027 · Rajmata Developers LLP

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026