MahaRERA Property Intelligence · Mumbai Suburban

GULRAJ TRINITY

P51800005013 · GOREGAON · promoter Reliable Builders And

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP51800005013
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Reliable Builders And is the promoter of record on 37 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~49.2% of the estimated project cost incurred as of the last certificate (₹75.98 Cr spent against a ₹154.33 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~49.2% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 14 homes filed with MahaRERA, 10 are sold/booked (9 with registered agreements + 1 booked) and 4 remain available (~71% sold) — selling steadily. Buyers have committed ₹1.16 Cr in agreement value so far. Of that, ₹17.17 Lakh (~15%) is already collected, ₹98.83 Lakh receivable — a read on how far along these sales really are. Note: the project registers 47 homes in total, but this sold/unsold inventory filing covers only 14 of them — the other 33 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1102717 sqft (66.63 sqm)-
Podium10420 sqft (39.04 sqm)-
Podium10420 sqft (39.04 sqm)-
Podium9286 sqft (26.61 sqm)-

⚠ The inventory filing also declares: 23 reserved and 10 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23 and 47 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
GULRAJ TRINITY - SALE BUILDING1G+2324-
LAXMI NAGAR SRA CO OP HSG SOCIETY LTD1G+2223-

Unit mix on the filing: 2 residential and 45 non-residential (shops/offices).

Complaints & Orders

31 complaints are on the MahaRERA record for this project, with orders passed in 26. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000029263010/09/2022PRADIP SHRIPAT PATANKAR vs RELIABLE BUILDERS & DEVELOPERSorder passed
CC00600000001238511/12/2017Yugesh@Vivekanand P Vyas vs M/s Reliable Builders and Developersorder passed
CC00600000020945920/12/2021RADHAKRISHNAN MENON vs Reliable Builders and Developersorder passed
CC00600000019906717/11/2021Ajay Jaiswal vs Ms Reliable Builders & Developersorder passed
CC00600000019637001/04/2021Bhavin Pravinbhai Vora vs Reliable Builders & Developersorder passed
CC00600000019802118/08/2021SHREE MANOHAR GAWAS vs M/S RELAIBLE BUILDERS & DEVELOPERSorder passed
CC00600000034423205/02/2023Vipin Choudhary vs Ms Reliable Builders & Developersorder passed
CC00600000039556110/05/2023ASWAD PURNENDU GHANEKAR vs RELIABLE BUILDER & DEVELOPERorder passed
CC00600000039556310/05/2023RAJESH PATHAK vs RELIABLE BUILDER & DEVELOPERorder passed
CC00600000039569813/05/2023TANMAY AGARWAL vs RELIABLE BUILDER & DEVELOPERorder passed
CC00600000039578713/05/2023VINOD BOMB vs RELIABLE BUILDER & DEVELOPERorder passed
CC00600000039605002/06/2023Mr Surendra Prasad Mr Santosh Kumar Ms Archana Pandit vs Reliable Builders and Developersorder passed
CC00600000039613817/06/2023Noor Jahan Asif Ahmed Shaikh vs Reliable Builders and Developersorder passed
CC00600000039628216/06/2023Sweta Suresh Singhal vs Reliable Builders and Developersorder passed
CC00600000039675724/07/2023Malavika Apurva Gupta vs RELIABLE BUILDERS AND DEVELOPERSorder passed
CC00600000039693415/09/2023MALA M JAIN vs RELIABLE BUILDERS AND DEVELOPERSorder passed
CC00600000039765429/09/2023Satish Chhabildas Karolia and Shaila Satish Karolia vs Reliable Builders & Developersorder passed
CC00600000039776011/10/2023ANANT KAMALAKANT PHATARPEKAR vs RELIABLE BUILDER & DEVELOPERorder passed
CC00600000039779711/10/2023ANANT KAMALAKANT PHATARPEKAR vs RELIABLE BUILDER & DEVELOPERorder passed
CC00600000042956214/03/2024Dr. Ravindra Bhardwaj vs M/s Reliable builders and developersorder passed
CC00600000042956708/03/2024Sajid Ali Shaikh vs Reliable Builders and Developersorder passed
CC00600000042956908/03/2024Mr Navdeep Singh Sahni and Mrs Savy Myne vs Reliable Builders and Developersorder passed
CC1240069807/11/2024Zubair Ahmed Syed vs M/S RELIABLE BUILDERS AND DEVELOPERSorder passed
CC1250174328/05/2025Neelam Chaudhory vs M/S RELIABLE BUILDERS AND DEVELOPERSorder passed
CC1250219702/07/2025Mansi Jain vs M/S RELIABLE BUILDERS AND DEVELOPERSorder passed
CC1250322112/09/2025Ankit Mahesh Jain vs M/S RELIABLE BUILDERS AND DEVELOPERSorder passed
CC1260210210/04/2026SHYAM AWASTHI vs M/S RELIABLE BUILDERS AND DEVELOPERSpending / no order on file
CC1260215912/04/2026sheetal suresh kale vs M/S RELIABLE BUILDERS AND DEVELOPERSpending / no order on file
CC1260270309/05/2026Mahendra Kumar Akshaivar Bharati vs Diwalar Vittal Shettypending / no order on file
CC1260274011/05/2026Mahendra Kumar Akshaivar Bharati vs M/S RELIABLE BUILDERS AND DEVELOPERSpending / no order on file
CC1260301221/05/2026SREEGIRIRAJU ADITYA vs M/S RELIABLE BUILDERS AND DEVELOPERSpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202530 Jun 2022DUE TO VERY SLUGGISH REAL ESTATE MARKET AND VERY POOR SALE OF FLATS AND EXTREMELY POOR FUND FLOW OF PROJECT, WE WOULD NOT BE ABLE TO COMPLETE THE PROJECT IN TIME. THEREFORE WE WOU
31 Dec 202531 Dec 2023DUE TO VERY SLUGGISH REAL ESTATE MARKET AND VERY POOR SALE OF FLATS AND EXTREMELY POOR FUND FLOW OF PROJECT, WE WOULD NOT BE ABLE TO COMPLETE THE PROJECT IN TIME. THEREFORE WE WOU
31 Dec 202531 Dec 2025DUE TO COVID 19 NOT ABLE TO COMPLETE OUR PROJECT PLEASE GRANT US EXTENSION TILL 31/12/2025

Location, Land & Connectivity

Located at GOREGAON, GOREGAON, Andheri, Mumbai Suburban, 400104. Per the filed land record, the plot is bounded to the north by 18 30 MTR WIDE DP ROAD, to the south by PLOT NO BD3 AND BD 4, to the east by GARDEN ESTATE BUILDING and to the west by OPEN PLOT AND INDUSTRIAL BUILDING. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon West

Giriraj
possession by Jul 2026 · Parshva Associates
Sejal Kajal Apartment CHS LTD
possession by Jul 2026 · Neminath Realtors
Goregaon Vihar Darshan CHS LTD
possession by Aug 2026 · Silver Lifespaces Private Limited
Atria Arshabharat
possession by Aug 2026 · Dharti Aakar Realty
Hitendra Dhamm Shabha Co-Operative Housing Society Limited
possession by Sep 2026 · Crystal Construction Company
Sahakar Revanta
possession by Sep 2026 · Sahakar Builders & Developers

Major developers building in Goregaon West

Other RERA-registered projects in Mumbai Suburban

Gulzar Apartment
declared completion Oct 2020 · Gulzar Ahmed Ainul Haque Shaikh
Gumpha Darshan C CO-Operative Housing Society LTD
declared completion Dec 2023 · Samarpan Buildtech LLP
Gundecha Asta Phase I
declared completion May 2018 · Anaya Infrastructure Pvt. Ltd.
Gundecha Desire
declared completion Dec 2019 · Rockline Developers Pvt. Ltd.
Gundecha Greens Phase 1
declared completion Dec 2022 · Kashtamandup Developers PVT LTD
Gundecha Rexon Suites Phase 1
possession by Oct 2028 · Anaya Infrastructure PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026