Mumbai/Project record

MahaRERA · the public record

HARI HEIGHTS

TILAK CHOWK · NASIM NIYAZ KHAN

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700016617

Delivery and registration

When is the project declared for completion?

HARI HEIGHTS is registered with MahaRERA as P51700016617 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700016617
Registered on25 May 2018
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HARI HEIGHTS record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Nasim Niyaz Khan is the promoter of record on 6 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HARI HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
HARI HEIGHTS1G+931 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at TILAK CHOWK, VALIPEER ROAD, Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by TILAK CHOWK ROAD, to the south by WADHAWA GANESH SOCIETY, to the east by KOHINOOR APARTMENT and to the west by WADHAWA GANESH SOCIETY. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Nasim Niyaz Khan is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Nasim Niyaz Khan

Other RERA-registered projects in Kalyan

Bhushan Anand CO OP HSG SOC
possession by Sep 2026 · Dinesh Laxman Sonavane
Ishanvi Ashapura Tower
possession by Sep 2026 · Ishanvi Ashapura Developers
Keshar Aagan Cooperative Housing Society
possession by Sep 2026 · Gagan Homes
Mohan Deep
possession by Sep 2026 · Sunil Purushottam Deshmukh
Parshuram Tower
possession by Sep 2026 · Moreshwar Constructions
Ritz Phase II Commercial Tower D
possession by Sep 2026 · Vikas Harakchand Jain

Major developers building in Kalyan

Other RERA-registered projects in Thane

Hari Krupa Residency, Kharde, Shahapur
declared completion Jul 2023 · Harikrupa Buildcon LLP
Hari Niwas
declared completion Jun 2024 · Hari Krishna Enterprise
Hari Shrushti
possession by Dec 2027 · Shrushti Creators
Hari Shrushti Wing A Phase II
possession by Dec 2030 · Shrushti Creators
Hari Vijay Lawns Building No.2
declared completion Dec 2022 · Creative Construction
Harihar Darshan
possession by Dec 2026 · Borgaonkar Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026