Mumbai/Project record

MahaRERA · the public record

HARSH KUSUM RESIDENCE

DADAR WEST · TANISHQUE INFRASTRUCTURE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900079015

Delivery and registration

When is the project declared for completion?

HARSH KUSUM RESIDENCE is registered with MahaRERA as P51900079015 and the promoter has declared completion for 30 Jun 2025.

30 Jun 2025

declared completion

15months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900079015
Registered on31 Jan 2025
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HARSH KUSUM RESIDENCE record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HARSH KUSUM RESIDENCE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
HARSH KUSUM RESIDENCE1G+9-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Small Causes CourtTER NO 15/20232023Pending
City Civil Court0102925/20242024Pending

Location, Land & Connectivity

Located at DADAR WEST, TPS -IV, MAHIM - GN WARD, PORTUGUESE CHURCH ROAD, Mumbai, Mumbai Suburban, 400028. Per the filed land record, the plot is bounded to the north by PLOT NO 299, to the south by ROAD 7 POINT 620 METER, to the east by PLOT NO 297 and to the west by PLOT NO 300 AND 301. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar West

Arihant Tower
possession by Sep 2026 · Mehta Developers
Palette
possession by Sep 2026 · Suraj Estate Developers LTD
Vijayshree
possession by Sep 2026 · Sugee Eighteen Developers LLP
Yash Trinity
possession by Sep 2026 · Bhalchandra Vinayak Wadnerkar
Sugee Sukrut
possession by Oct 2026 · Sugee Nine Developers LLP
1891 Ekam Parkk
possession by Dec 2026 · Nascent Developers

Major developers building in Dadar West

Other RERA-registered projects in Mumbai City

Harsh Oasis
possession by Jul 2029 · Harsh Developers & Infrastructure LL
Harsh Sapphire
possession by Mar 2028 · Harsh Realty Builders & Developers
Harsh Tulip
possession by Oct 2026 · Harsh Developers & Infrastructure LL
Hasan ALI
possession by Dec 2028 · Citymaker Builders Private Limited
Haware Intelligentia Sigma South Jvlr Wing B
declared completion Dec 2024 · Suresh Kashinath Haware
HBS Marineview
declared completion Dec 2025 · HBS Seaview Pvt Ltd

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026