Mumbai/Project record

MahaRERA · the public record

HEARTLAND

BAMANGAON · SHILPA PRATAP GAMBHIR

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000024424

Delivery and registration

When is the project declared for completion?

HEARTLAND is registered with MahaRERA as P52000024424 and the promoter has declared completion for 01 Mar 2024.

01 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000024424
Registered on12 Feb 2020
Promoter-declared completion01 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HEARTLAND record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In HEARTLAND, 0 of 31 plots filed with MahaRERA are recorded as sold or booked, about 0%, and 31 remain available.

0%sold

0 of 31 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HEARTLAND in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BAMANGAON, KAWIR, Alibag, Raigarh, 402204. Per the filed land record, the plot is bounded to the north by GAT NUMBER 485, to the south by GAT NUMBER 477, to the east by GAT NUMBER 315 and to the west by GAT NUMBER 485. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nagaon

Nilaya
possession by Dec 2026 · Fourthstreet Consultancy LLP
Suki-Nihon-Phase 2
possession by Jun 2027 · Nimesh Kirti Chhatbar
Coral Bay
possession by Dec 2028 · Dynamix Vacation Resorts Private Limited
Coral Court
possession by Dec 2028 · Dynamix Vacation Resorts Private Limited
Coral Nest
possession by Dec 2028 · Dynamix Vacation Resorts Private Limited
Creata Harmony
possession by Dec 2028 · Creata Lifespaces Llp

Major developers building in Nagaon

Other RERA-registered projects in Raigarh

Heaven Arcade
possession by Dec 2026 · Maruti Infra Developers
Hecc-SAI City
possession by Dec 2026 · Liyakat Anwar Hafiz
Heetraj Heights
possession by Mar 2027 · Yamutai Balaji Vichare
HEM Sanwariya
possession by Mar 2027 · Shyamsunder Satyanarayan DAD
Herai Complex - B Wing, Hajwane Complex- C Wing
possession by Dec 2026 · Akhtar Ahmed Lambade
Heramb Residency
possession by May 2028 · Shree Siddhivinayk Group

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026