Hill Park Co-Operative Housing Society Limited
Vadavali · Unigrow On Infrastructure Housing LLP
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Aug 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700079449
Delivery and registration
When is the project declared for completion?
Hill Park Co-Operative Housing Society Limited is registered with MahaRERA as P51700079449 and the promoter has declared completion for 31 Aug 2028.
31 Aug 2028
declared completion
23months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700079449 |
| Registered on | 06 Mar 2025 |
| Promoter-declared completion | 31 Aug 2028 |
| Current status | Certificate Signed |
| Against today | 23 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Hill Park Co-Operative Housing Society Limited record 5 quarterly progress reports since registration.
5quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.
Construction
How much construction cost has been reported?
In Hill Park Co-Operative Housing Society Limited, ₹0 of a declared ₹8.10 Cr estimated project cost is reported as incurred, about 0.0%, as at the last certified filing with MahaRERA.
0.0%
₹0
of ₹8.10 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Hill Park Co-Operative Housing Society Limited, 0 of 47 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 47 remain available.
0%sold
0 of 47 homes
Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 89 homes in total, while this sold/unsold inventory filing covers 47 of them.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Hill Park Co-Operative Housing Society Limited in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 20 September 2026
What the filings record, home by home
Read from MahaRERA on 20 September 2026
No home in Hill Park Co-Operative Housing Society Limited carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 47 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 5,463 a sq ft typical, over Rs 5,463 to Rs 7,507.
A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.
The Reckoner Record lists all 47 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 89 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Hill Park Co-Operative Housing Society Limited | 1 | G+8 | 89 | - |
Unit mix on the filing: 79 residential and 10 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at Vadavali, Vadavali, Kurla, Mumbai Suburban, 421501. Per the filed land record, the plot is bounded to the north by Survey No 33 Hissa No 1 Part, to the south by Survey No 33 Hissa No 1 Part, to the east by Public Road and to the west by Survey No 33 Hissa No 1 Part. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~32 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 32 km |
| Andheri MIDC / SEEPZ | 35 km |
| Chhatrapati Shivaji Int'l Airport | 37 km |
| Bandra Kurla Complex (BKC) | 37 km |
| Lower Parel / Worli business district | 44 km |
| Nariman Point / Fort | 49 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.