Mumbai/Project record

MahaRERA · the public record

HILL VIEW COMPLEX

Gut no. 23/2 · Nirmal Singh Chandan Singh Saini

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 May 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 May 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000019428

Delivery and registration

When is the project declared for completion?

HILL VIEW COMPLEX is registered with MahaRERA as P52000019428 and the promoter has declared completion for 30 May 2023.

30 May 2023

declared completion

40months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000019428
Registered on29 Jan 2019
Promoter-declared completion30 May 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HILL VIEW COMPLEX record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Nirmal Singh Chandan is the promoter of record on 46 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

46projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HILL VIEW COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Shree Sai Kripa1G+431 May 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Gut no. 23/2, Gut no. 23/2, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by Road and Gut no 22, to the south by Gut no 24 and Gut no 23-1, to the east by Gut no 22 and Proposed Road and to the west by Gut no 23 and Gut no 22. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Arihant Clan Aalishan Phase I
possession by Sep 2026 · Arihant Vatika Realty Private Limited
Balaji Heritage
possession by Sep 2026 · Buildfox Realty LLP
Delta Hills
possession by Sep 2026 · Shree Ganesh Enterprises
Delta Riviera
possession by Sep 2026 · Shreenathji Organisers Pvt. Ltd.
GAJ Oasis
possession by Sep 2026 · Shiv Builders AND Developers
Green View
possession by Sep 2026 · Siddhivinayak Developers

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Hill View Residency
declared completion Jul 2024 · Mcbool Realtors
Hillcrest
possession by Dec 2027 · Erdamor Realty LLP
Hills N Mills
declared completion Dec 2020 · Iconstruct Private Limited
Hills Regency
declared completion Dec 2019 · Tech Nova Enterprises
Hillside Space
declared completion Dec 2022 · Space Housing
Himalaya Gardens
possession by Mar 2027 · Himalaya Builders AND Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026