Mumbai/Project record

MahaRERA · the public record

HIRAL SHREE SAMARTH

Mumbai Suburban · HIRAL HOMES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700012157

Delivery and registration

When is the project declared for completion?

HIRAL SHREE SAMARTH is registered with MahaRERA as P51700012157 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700012157
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HIRAL SHREE SAMARTH record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Hiral Homes is the promoter of record on 27 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

27projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HIRAL SHREE SAMARTH in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
HIRAL SHREE SAMARTH BUILDING NO IV1G+6-
HIRAL SHREE SAMARTH BUILDING NO V1G+6-

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for HIRAL SHREE SAMARTH, with orders passed in 0 of them.

3complaints

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000030371728/04/2023ANILKUMAR VIJAYPAL SINGH vs M/S. HIRAL HOMES LLPpending / no order on file
CC00600000039651702/07/2023SAVITA ANILKUMAR SINGH vs MS HIRAL HOMES LLPpending / no order on file
CC1260092919/02/2026Vishal Rajendra Patel vs HIRAL HOMESpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020we have applied for furhter cc, for pending work

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 401107. Per the filed land record, the plot is bounded to the north by SURVEY NO 21 HISSA 2, to the south by SURVEY NO 88, to the east by SURVEY NO 86 and to the west by SURVEY NO 21 HISSA 3. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ16 km
Powai / Hiranandani business park17 km
Chhatrapati Shivaji Int'l Airport20 km
Bandra Kurla Complex (BKC)23 km
Lower Parel / Worli business district31 km
Nariman Point / Fort39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Hiral Homes is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Hiral Homes

Hiral Homes
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Mira Road East

Beaumonde
possession by Sep 2026 · Kanungo Property
Rassaz Greens Tower C D AND E
possession by Dec 2026 · Rassaz Infrastructure Private Limited
Coral
Deregistered by MahaRERA · possession by Dec 2026 · Nilesh Shantilal Tank
JP North Aviva
possession by Dec 2026 · JP Infra Realty Private Limited
Prithvi Sneh
Deregistered by MahaRERA · possession by Dec 2026 · Prithvi Buildworth Constructions
Shree RAM Heights
possession by Dec 2026 · Vavya Enterprises

Major developers building in Mira Road East

Other RERA-registered projects in Thane

Hiranandani Westgate - Hampstead
possession by Dec 2032 · Shoden Developers Private Limited
Hiranandani Westgate Phase 1
possession by Oct 2031 · Shoden Developers Private Limited
Hiranandani Woodspring Bldg A-Oakwood Bldg B-Bridgewood Bldg C-Greenwood
possession by Jan 2028 · Golden Mile Builders LLP
Hitech Park
possession by Dec 2029 · Silverleaf Buildcon
Hitesh Devesh Paradise
declared completion Dec 2021 · JAI Ambe Construction
Hiya Avenue
possession by Mar 2029 · Vinod Lalchandji Mehta

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026