Mumbai/Project record

MahaRERA · the public record

HIRAL LEGACY

Mumbai Suburban · HIRAL HOMES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800008326

Delivery and registration

When is the project declared for completion?

HIRAL LEGACY is registered with MahaRERA as P51800008326 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800008326
Registered on18 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HIRAL LEGACY record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Hiral Homes is the promoter of record on 27 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

27projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HIRAL LEGACY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
HIRAL LEGACY1G+14-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for HIRAL LEGACY, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000007816920/02/2019Niren Soni vs Hiral Homes LLPorder passed
CC00600000007830628/02/2019Ashok Ghanshyamdas Parekh vs Hiral Homesorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020FURTHER WORK IS PENDING, WE HAVE RECEIVED IOD FROM COMPETENT AUTHORITY, WE ATTACHING THE SAME

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by CTS 553, to the south by CTS 550, to the east by D P ROAD and to the west by WHITE FIELD BUILDING. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Hiral Homes is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Hiral Homes

Hiral Homes
Past its declared completion dateThane

Other RERA-registered projects in Kandivali West

Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon
SAI Elegance
possession by Sep 2026 · Nirav Thaker Buildcon LLP
Shree Vallabh
possession by Sep 2026 · Mamtora Enterprise
Yamuna Maharani Heights
possession by Sep 2026 · K B Associates
Goyal Aspire
possession by Oct 2026 · Nexa Buildcon LLP

Other RERA-registered projects in Mumbai Suburban

Hiranandani Maitri Park Phase 1
possession by Mar 2031 · Shoden Developers Private Limited
Hirani Elixir
possession by Mar 2028 · OM SJK Realty LLP
Hirani Villa
declared completion May 2026 · AMI Infra Projects Private Limited
Hiranmay Niwas CO-Operative Housing Society Limited
declared completion Jan 2025 · Samarpan Homes & Developers
Hiranyakeshi Heights
possession by Dec 2030 · Multi Space Constructions LLP
Hitendra Dhamm Shabha Co-Operative Housing Society Limited
possession by Sep 2026 · Crystal Construction Company

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026