Hiranandani Maitri Park Phase 1

Chembur · SHODEN DEVELOPERS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

298units filed as unsoldInventory · 20 September 2026
31 Mar 2031declared completionMahaRERA registration · read 02 Jul 2026
694registered unitsMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1180002600200

Delivery and registration

When is the project declared for completion?

Hiranandani Maitri Park Phase 1 is registered with MahaRERA as PR1180002600200 and the promoter has declared completion for 31 Mar 2031.

31 Mar 2031

declared completion

54months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPR1180002600200
Registered on18 Apr 2026
Promoter-declared completion31 Mar 2031
Current statusCertificate Signed
Against today54 months to the declared date

Promoter record

What else is this promoter on record for?

Shoden Developers is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 02 Jul 2026

Sales

How much has actually been sold?

In Hiranandani Maitri Park Phase 1, 0 of 335 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 335 remain available.

0%sold

0 of 335 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 694 homes in total, while this sold/unsold inventory filing covers 335 of them.

Source · MahaRERA sold/unsold inventory filing · read 02 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 37 homes carry one, and 298 of the 335 are recorded unsold. Since we started watching this ledger, 37 homes have moved out of the unsold list, most recently on 04 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
102762 sqftRs 50,152 a sq ft typical, over Rs 44,150 to Rs 52,99513 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Hiranandani Maitri Park Phase 1, 211 of the 298 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 297 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22 and 694 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Tower - 011G+2176-
Tower - 021G+2178-
Tower - 031G+2180-
Tower - 041G+2180-
Tower - 051G+2188-
Tower - 061G+2238-
Tower - 071G+2238-
Tower - 081G+2238-
Tower - 091G+42-
Tower - 101G+2034-
Tower - 111G+42-
Tower - 121G+2172-
Tower - 131G+2154-
Tower - 141G+1014-

Unit mix on the filing: 661 residential and 33 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court72402019Ongoing
City Civil Court1042042024Ongoing
Bombay High Court28832026Ongoing

Location, Land & Connectivity

Located at Chembur, V N Purav Marg (Sion Trombay Road), Kurla, Mumbai Suburban, 400071. Per the filed land record, the plot is bounded to the north by 36.60 mt V N Purav Marg (Sion Trombay Road), to the south by CTS No 1814, to the east by CTS No 146, CTS No 148, CTS No 149, CTS No 150 and CTS No 151 and to the west by 9.15 Mt Wide DP Road Lalwadi Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport6 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district10 km
Andheri MIDC / SEEPZ10 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shoden Developers Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Shoden Developers Private Limited

Shoden Developers Private Limited
FlaggedThane
Shoden Developers Private Limited
FlaggedThane

Other RERA-registered projects in Chembur

Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited
Laxmina Krishna Niwas
possession by Oct 2026 · Laxmina Argentum Realties Private Lim
Safal SAI AND Safal Sainath
possession by Oct 2026 · Mangalnath Developers PVT LTD

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Hirani Elixir
possession by Mar 2028 · OM SJK Realty LLP
Hirani Villa
declared completion May 2026 · AMI Infra Projects Private Limited
Hiranmay Niwas CO-Operative Housing Society Limited
declared completion Jan 2025 · Samarpan Homes & Developers
Hiranyakeshi Heights
possession by Dec 2030 · Multi Space Constructions LLP
Hitendra Dhamm Shabha Co-Operative Housing Society Limited
possession by Sep 2026 · Crystal Construction Company
Hitesh Apartment
declared completion Jul 2023 · Magnum Cylinders Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026