MahaRERA · the public record
HITECH SADGURU KRUPA
PUSHPAK NODE PANVEL NAVI MUMBAI · HI TECH REALTORS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Mar 2023
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52000028877
Delivery and registration
When is the project declared for completion?
HITECH SADGURU KRUPA is registered with MahaRERA as P52000028877 and the promoter has declared completion for 30 Mar 2023.
30 Mar 2023
declared completion
42months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52000028877 |
| Registered on | 05 Apr 2021 |
| Promoter-declared completion | 30 Mar 2023 |
| Current status | Certificate Signed |
| Against today | about 42 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HITECH SADGURU KRUPA record 8 quarterly progress reports since registration.
8quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for HITECH SADGURU KRUPA in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| HITECH SADGURU KRUPA | 1 | G+6 | - |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at PUSHPAK NODE PANVEL NAVI MUMBAI, PLOT NO 455 SECTOR 24, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by PLOT NO 455A, to the south by 11 MTR WIDE ROAD, to the east by PLOT NO 433B and to the west by 33 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.