Hive suites

Dadar · Shree Richa Realtors

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900012718

Delivery and registration

When is the project declared for completion?

Hive suites is registered with MahaRERA as P51900012718 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

9months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900012718
Registered on07 Sep 2017
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today9 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Hive suites record 37 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Hive suites in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
Hive Suites1G+2430 Dec 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Hive suites, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250424201/12/2025RANJANA PEDNEKAR vs Shree Richa Realtorsorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2027Due to Company financial and COVID project was delay we would request you to approve the extension as we have arrange fund

Location, Land & Connectivity

Located at Dadar, Gokhale Road, Mumbai City, Mumbai City, 400028. Per the filed land record, the plot is bounded to the north by CS no 1782 and 310, to the south by CS no 1587, to the east by Shivaji park road and to the west by Ranade road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district3 km
Bandra Kurla Complex (BKC)6 km
Chhatrapati Shivaji Int'l Airport8 km
Nariman Point / Fort11 km
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar West

Arihant Tower
possession by Sep 2026 · Mehta Developers
Palette
possession by Sep 2026 · Suraj Estate Developers LTD
Vijayshree
possession by Sep 2026 · Sugee Eighteen Developers LLP
Yash Trinity
possession by Sep 2026 · Bhalchandra Vinayak Wadnerkar
Sugee Sukrut
possession by Oct 2026 · Sugee Nine Developers LLP
1891 Ekam Parkk
possession by Dec 2026 · Nascent Developers

Major developers building in Dadar West

Other RERA-registered projects in Mumbai City

Horizon Tower
declared completion Oct 2020 · Horizon Realty
Hubtown - Celeste
possession by Jul 2029 · Nayan Real Estate Private Limited
Hubtown Harmony A Wing
declared completion Dec 2024 · Heet Builders Private Limited
Hubtown Harmony B Wing
declared completion Dec 2024 · Heet Builders Private Limited
Hubtown Harmony Retail
declared completion Dec 2023 · Heet Builders Private Limited
Hubtown Vedant- 14th To 18th Floor
declared completion Dec 2025 · Citywood Builders Private Limited

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.