Mumbai/Project record

MahaRERA · the public record

Horizon Pearl II

Thane · KM Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

55units filed as unsoldInventory · 20 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
151registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700079782

Delivery and registration

When is the project declared for completion?

Horizon Pearl II is registered with MahaRERA as P51700079782 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700079782
Registered on26 Mar 2025
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Horizon Pearl II record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In Horizon Pearl II, ₹7.20 Cr of a declared ₹47.97 Cr estimated project cost is reported as incurred, about 15.0%, as at the last certified filing with MahaRERA.

15.0%

₹7.20 Cr

of ₹47.97 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Horizon Pearl II, 33 of 92 homes filed with MahaRERA are recorded as sold or booked, about 36%, and 59 remain available.

36%sold

33 of 92 homes

₹17.57 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹6.78 Cr (about 39%) is recorded as collected and ₹10.79 Cr as receivable. The project registers 151 homes in total, while this sold/unsold inventory filing covers 92 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 33 registered agreements, the effective carpet rate is ₹11,153/sqft, with eight in ten falling between ₹11,061 and ₹12,342 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 59 not for sale.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 37 homes carry one, and 55 of the 151 are recorded unsold. Since we started watching this ledger, 5 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
201403 sqftRs 44.90 lakh typical, over Rs 44.53 lakh to Rs 52.24 lakh25 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Horizon Pearl II, every one of the 55 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 54 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+28 and 151 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Horizon Pearl II - Wing A1G+46-
Horizon Pearl II - Wing B1G+28145-

Unit mix on the filing: 151 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Thane, Owale, Thane, Thane, 400615. Per the filed land record, the plot is bounded to the north by adj C T S 272, to the south by adj C T S 344, to the east by adj C T S 269 and 12 00 MW Right of Way and to the west by adj C T S 274. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ18 km
Chhatrapati Shivaji Int'l Airport22 km
Bandra Kurla Complex (BKC)25 km
Lower Parel / Worli business district33 km
Nariman Point / Fort41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Owale

ACE Aristo
possession by Oct 2026 · Gaurav Land Corporation
Metro Hive D-1
possession by Dec 2026 · Vihang Infrastructure PVT LTD
Vihang Plaza - A Commecial
possession by Dec 2026 · Vihang Enterprises
Vihang Woods
possession by Dec 2026 · Vihang Enterprises
Ace Enclave
possession by Dec 2026 · Ace Signature Homes LLP
Cascade Avenue Bellagio
possession by Dec 2026 · Aarsh Construction

Major developers building in Owale

Other RERA-registered projects in Thane

Hotel
declared completion Dec 2024 · Roma Builders Private Limited
Hubtown Greenwoods E Wing
declared completion Jan 2021 · Hubtown Limited
Hubtown Siddhi
declared completion Jul 2023 · Hubtown Limited
Huda Park
declared completion Dec 2025 · Huda Construction
Humsaaz Homes
possession by Jun 2027 · Humsaaz Homes LLP
Hussain Excellency
possession by Dec 2030 · LIS India Construction Company PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026