31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800001202

Delivery and registration

When is the project declared for completion?

Hubtown Sunmist A 6th to Above Floor is registered with MahaRERA as P51800001202 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800001202
Registered on27 Jul 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Hubtown Sunmist A 6th to Above Floor record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Hubtown Limited is the promoter of record on 20 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

20projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Hubtown Sunmist A 6th to Above Floor in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Hubtown Sunmist A 6th to Above Floor1G+1431 Dec 2019

Legal and disputes

What disputes are disclosed?

8 complaints are on the MahaRERA record for Hubtown Sunmist A 6th to Above Floor, with orders passed in 8 of them.

8complaints

8with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002306025/01/2018Harshad Bhanushali vs Hubtown Limitedorder passed
CC00600000002356219/03/2018Vijay S Saokar vs Hubtown Limitedorder passed
CC00600000002376617/03/2018Samir Kadam vs Hubtown Limitedorder passed
CC00600000005563603/08/2018RAJ BRIJMOHAN PODDAR vs Hubtown Limitedorder passed
CC00600000005563803/08/2018RAJ BRIJMOHAN PODDAR vs Hubtown Limitedorder passed
CC00600000005568217/09/2018MRS. PRISCILLA RODRIGUES vs M/S. HUBTOWN LIMITEDorder passed
CC00600000019829909/09/2021Uday Kashinath Patil vs Hubtown Limitedorder passed
CC00600000034419502/02/2023Hubtown Limited vs Uday Kashinath Patilorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High CourtSuit No 56 of 20162016Pending

Location, Land & Connectivity

Located at On Andheri Juhu Link Road, Opp.Hubtown Solaris, Andheri East, Off. Teli Gali, Kurla, Mumbai Suburban, 400069. Per the filed land record, the plot is bounded to the north by CTS 427 8, to the south by CTS 427 2, to the east by CTS 425 426 and to the west by CTS 427 3. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ3 km
Chhatrapati Shivaji Int'l Airport3 km
Bandra Kurla Complex (BKC)6 km
Powai / Hiranandani business park6 km
Lower Parel / Worli business district13 km
Nariman Point / Fort21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Hubtown Limited is the promoter on 19 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Hubtown Limited project & its RERA track record →

Other flagged projects by Hubtown Limited

Hubtown Limited
FlaggedMumbai Suburban
Hubtown Limited
FlaggedMumbai Suburban
Hubtown Limited
FlaggedMumbai Suburban
Hubtown Limited
FlaggedMumbai Suburban
Hubtown Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Andheri East

Anamika
possession by Sep 2026 · NEW India Constructions
Romell Myra
Deregistered by MahaRERA · possession by Sep 2026 · Romell Properties Private Limited
Romell Orbis
possession by Sep 2026 · Romell Properties Private Limited
Amey Apartments
possession by Oct 2026 · Amey Realty AND Construction LLP
Elegant Residency
possession by Dec 2026 · Elegant Builders AND Developers
Girnar Residency Wing B Phase 1
possession by Dec 2026 · Nidhaan Realty LLP

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

HUM Durga
possession by Dec 2026 · HUM Developers Private Limited
HUM Emerald Heights
possession by Dec 2029 · HUM Developers Private Limited
Hum Galaxy Heights
possession by Dec 2030 · HUM Developers Private Limited
Hum GS Heights
possession by Dec 2031 · HUM Developers Private Limited
Hum Laxmi
possession by Dec 2030 · HUM Developers Private Limited
HUM Sapphire
possession by Dec 2030 · HUM Developers Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.