Mumbai/Project record

MahaRERA · the public record

HUM SUB CHSL

Shankar Lane, Kandivali (West) · SHRADDHARPAN DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800004487

Delivery and registration

When is the project declared for completion?

HUM SUB CHSL is registered with MahaRERA as P51800004487 and the promoter has declared completion for 30 Jun 2019.

30 Jun 2019

declared completion

87months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800004487
Registered on09 Aug 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 87 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for HUM SUB CHSL record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for HUM SUB CHSL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
HUM SUB CHSL1G+930 Jun 2018

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for HUM SUB CHSL, with orders passed in 2 of them.

3complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000008977619/06/2019Rashmi H Tejani vs Messers Shraddharpan Developersorder passed
CC00600000019803821/08/2021Zarna Samin Gorasia vs SHRADDHARPAN DEVELOPERSorder passed
CC1260279213/05/2026Kirit Suba vs SHRADDHARPAN DEVELOPERSpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2019The above project is completed, as it can be seen from the Architects report dated 31-12-2018 that 100 % of the work has been completed, we are also submitting the Architects repor
30 Jun 201930 Jun 2019The above project is on the verge of completion, as it can be seen from the Architects report that 90 -95 % of the work has been completed. The cabling and electric metres for each

Location, Land & Connectivity

Located at Shankar Lane, Kandivali (West), Parmanand Mehta Marg, Borivali, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by By private plot no B, to the south by By private plot no F of Haribai D Chhaptar, to the east by By property of Atmaram Gangadas Merchant and to the west by By 20 ft wide private road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali West

Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon
SAI Elegance
possession by Sep 2026 · Nirav Thaker Buildcon LLP
Shree Vallabh
possession by Sep 2026 · Mamtora Enterprise
Yamuna Maharani Heights
possession by Sep 2026 · K B Associates
Goyal Aspire
possession by Oct 2026 · Nexa Buildcon LLP

Other RERA-registered projects in Mumbai Suburban

I.c. Maitri Menorah
possession by Mar 2029 · Ramas Realty
I.c.residency - 1
declared completion Dec 2023 · Vora Estates
I. C. Unique Chsl
declared completion Jan 2025 · Vasuprada Developers Private Limited
I Space Urban Vista
possession by Aug 2027 · RT Housing Private Limited & Shree S
I-Stay Tower - D
possession by Dec 2028 · I-Stay Housing Private Limited
I-Stay Tower-E
possession by Nov 2028 · I-Stay Housing Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026