I. C. UNIQUE CHSL

Borivali West · Vasuprada Developers Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

16 Jan 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

16 Jan 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800045959

Delivery and registration

When is the project declared for completion?

I. C. UNIQUE CHSL is registered with MahaRERA as P51800045959 and the promoter has declared completion for 16 Jan 2025.

16 Jan 2025

declared completion

20months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800045959
Registered on15 Jun 2022
Promoter-declared completion16 Jan 2025
Current statusCertificate Signed
Against todayabout 20 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for I. C. UNIQUE CHSL record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for I. C. UNIQUE CHSL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
I C Unique CHSL1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered16 Jan 2025We, Vasuprada Developers Pvt. Ltd., the Promoter of the project "I.C. UNIQUE CHSL", wish to bring to your kind attention that we have successfully completed the project on 16th Jan

Location, Land & Connectivity

Located at Borivali West, I C Colony Cross Road No.6, Mumbai, Mumbai Suburban, 400103. Per the filed land record, the plot is bounded to the north by CTS No 1015, to the south by CTS No 1018, to the east by CTS No 1017 and to the west by 9 mtrs existing road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali West

Borivali Madhumas Chsl
possession by Dec 2026 · Aadhunik Developers
Borivali SAI Hill CHS
possession by Dec 2026 · THE Green Venturez Realtors
Empire Fairmont
possession by Dec 2026 · Empire Realty
Maruti Residency
possession by Dec 2026 · OM Construction
Mascarenhas Apartment
Not filing quarterly progress reports · possession by Dec 2026 · SAI Universal Realtors & Developers
NEW Siddharth CO-Operative Housing Society LTD
possession by Dec 2026 · Not Available

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

I Space Urban Vista
possession by Aug 2027 · RT Housing Private Limited & Shree S
I-Stay Tower - D
possession by Dec 2028 · I-Stay Housing Private Limited
I-Stay Tower-E
possession by Nov 2028 · I-Stay Housing Private Limited
I-Stay Tower-F
possession by Oct 2028 · I-Stay Housing Private Limited
I-Stay Tower -G
possession by Jun 2028 · I-Stay Housing Private Limited
I Stay Tower - I Studio
possession by Jun 2028 · Starwing Real Estate Company

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026