MahaRERA Property Intelligence · Mumbai Suburban

IBIS

P51800005446 · promoter Bau Developers Private

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51800005446
Registered on11 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+33.

BuildingWingsFloorsDeclared completion
IBIS1G+33-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201831 Dec 2018WE HAVE RECEIVED CC FOR PROJECT DATED 15TH JANUARY 2015. FURTHER BUILDING IS OF 28TH FLOOR. CC FOR 26TH TO 28TH FLOOR RECEIVED ON DATED 18TH NOVEMBER 2017. FURTHER WE HAD RECEIVE

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by LALJI PADA, to the south by SERVICE ROAD, to the east by LINK ROAD and to the west by RENUKA NAGAR CHS LTD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ10 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport14 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district24 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali West

Primrose
possession by Jul 2026 · Kaustubh Construction Private Limited
Harmony
possession by Aug 2026 · Shreenath Associates
Laxmi Heights
possession by Sep 2026 · M/S Laxmi Lifespaces
Mahavir Majesty
possession by Sep 2026 · Mahavir Builders
Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon

Major developers building in Kandivali West

Other RERA-registered projects in Mumbai Suburban

Ibis At L And T Realty Elixir Reserve
possession by Dec 2026 · Larsen & Toubro Ltd.
Icon
possession by Dec 2027 · Raghu Leela Realtors Private Limited
Icon Belle VUE
declared completion Aug 2023 · Icon Developers
Iconic Residency
declared completion Mar 2026 · S K Housing
Icons 71
possession by Dec 2031 · Skyplus Real Estates Private Limited
Ideal Chsl
declared completion Dec 2019 · Neumec Infrastructure LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026