31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005446

Delivery and registration

When is the project declared for completion?

IBIS is registered with MahaRERA as P51800005446 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005446
Registered on11 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for IBIS record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for IBIS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+33.

BuildingWingsFloorsDeclared completion
IBIS1G+33-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2018WE HAVE RECEIVED CC FOR PROJECT DATED 15TH JANUARY 2015. FURTHER BUILDING IS OF 28TH FLOOR. CC FOR 26TH TO 28TH FLOOR RECEIVED ON DATED 18TH NOVEMBER 2017. FURTHER WE HAD RECEIVE

Location, Land & Connectivity

Located at Kandivali West, Kurla, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by LALJI PADA, to the south by SERVICE ROAD, to the east by LINK ROAD and to the west by RENUKA NAGAR CHS LTD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ10 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport14 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district24 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali West

Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon
SAI Elegance
possession by Sep 2026 · Nirav Thaker Buildcon LLP
Shree Vallabh
possession by Sep 2026 · Mamtora Enterprise
Yamuna Maharani Heights
possession by Sep 2026 · K B Associates
Goyal Aspire
possession by Oct 2026 · Nexa Buildcon LLP

Other RERA-registered projects in Mumbai Suburban

Ibis At L And T Realty Elixir Reserve
possession by Dec 2026 · Larsen & Toubro Ltd.
Icon
possession by Dec 2027 · Raghu Leela Realtors Private Limited
Icon Belle VUE
declared completion Aug 2023 · Icon Developers
Icon Opus 50
possession by Mar 2028 · Icon Developers Ritwal
Iconic Residency
declared completion Mar 2026 · S K Housing
Icons 71
possession by Dec 2031 · Skyplus Real Estates Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026