Mumbai/Project record

MahaRERA · the public record

ICON BELLE VUE

Chandawarkar Cr Rd 01 · ICON DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

0units filed as unsoldInventory · 13 September 2026
30 Aug 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Aug 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800009393

Delivery and registration

When is the project declared for completion?

ICON BELLE VUE is registered with MahaRERA as P51800009393 and the promoter has declared completion for 30 Aug 2023.

30 Aug 2023

declared completion

37months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800009393
Registered on22 Aug 2017
Promoter-declared completion30 Aug 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ICON BELLE VUE record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Icon Developers is the promoter of record on 133 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

133projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 23 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

Every home in ICON BELLE VUE is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 23 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 23 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
REBAN CHS LTD1G+23-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for ICON BELLE VUE, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250264530/07/2025NILESH V SHAH vs ICON DEVELOPERSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered28 Feb 2022Dear Sir, I/We the Promoters of the Project Sai Shanti Park Anand registered under project registration number P52000005784 do hereby declare that we had mentioned the revised
28 Feb 202230 Aug 2023Dear Sir, I/We the Promoters of the Project Sai Shanti Park Anand registered under project registration number P52000005784 do hereby declare that we had mentioned the revised

Location, Land & Connectivity

Located at Chandawarkar Cr Rd 01, Ramdas Sutrale Marg, Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by FP 65, to the south by FP 63, to the east by FP 60 and to the west by MCGM ROAD 60 RFT WIDE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ14 km
Powai / Hiranandani business park17 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Icon Developers is the promoter on 8 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Icon Developers project & its RERA track record →

Other flagged projects by Icon Developers

Icon Developers
Not filing quarterly progress reportsMumbai Suburban
Icon Developers
Past its declared completion dateMumbai Suburban
Icon Developers
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Borivali West

Gopal Terrace Co-Operative Housing Society LTD
possession by Sep 2026 · Polo Infra Developers Private Limited
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Sai Signature Spaces
possession by Sep 2026 · Ramachandran Munisawmy Narayan
Shikhhar
possession by Sep 2026 · Mahavir Land Developer
Swastik
possession by Sep 2026 · Reliance Corporation
Signet
possession by Oct 2026 · DG Builders

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

Icon Opus 50
possession by Mar 2028 · Icon Developers Ritwal
Iconic Residency
declared completion Mar 2026 · S K Housing
Icons 71
possession by Dec 2031 · Skyplus Real Estates Private Limited
Ideal Manohar CHS LTD
declared completion Feb 2026 · Faucett Developers
Iifl Centre
possession by Dec 2026 · Spenta Sun City Private Limited
Imperial Hava Hira
declared completion Jul 2026 · Shree SAI Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026