Mumbai/Project record

MahaRERA · the public record

JYOTIKA HEIGHTS

OPP. MCGM OFFICE, KANDIVALI - WEST, MUMBAI. · ICON DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Feb 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Feb 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800026763

Delivery and registration

When is the project declared for completion?

JYOTIKA HEIGHTS is registered with MahaRERA as P51800026763 and the promoter has declared completion for 29 Feb 2024.

29 Feb 2024

declared completion

31months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800026763
Registered on22 Oct 2020
Promoter-declared completion29 Feb 2024
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JYOTIKA HEIGHTS record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Icon Developers is the promoter of record on 133 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

133projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JYOTIKA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
SHREEJI SHARAN - JYOTIKA CHS LTD1G+1031 Aug 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at OPP. MCGM OFFICE, KANDIVALI - WEST, MUMBAI., M. G. CROSS ROAD NO - 02,, Borivali, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by CTS NO 1151, to the south by CTS NO 1152 B, to the east by CTS NO 1146 A and to the west by MCGM ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ20 km
Chhatrapati Shivaji Int'l Airport24 km
Bandra Kurla Complex (BKC)25 km
Lower Parel / Worli business district34 km
Nariman Point / Fort41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Icon Developers is the promoter on 8 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Icon Developers project & its RERA track record →

Other flagged projects by Icon Developers

Icon Developers
Not filing quarterly progress reportsMumbai Suburban
Icon Developers
FlaggedMumbai Suburban
Icon Developers
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Kandivali West

Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon
SAI Elegance
possession by Sep 2026 · Nirav Thaker Buildcon LLP
Shree Vallabh
possession by Sep 2026 · Mamtora Enterprise
Yamuna Maharani Heights
possession by Sep 2026 · K B Associates
Goyal Aspire
possession by Oct 2026 · Nexa Buildcon LLP

Other RERA-registered projects in Mumbai Suburban

Jyotsna Heritage Redevelopment Of The Dahisar R.k. Nayak Niwasi CHS LTD
declared completion Jun 2025 · M/S Shree Sainamah Homes LLP
K.e. Heights
possession by Dec 2027 · Khurshid Ebrahim & Sons
K.k.garment HUB
declared completion Mar 2025 · Shaista Khalil & Sons Developers Pri
K L Astoria
declared completion Dec 2025 · K L Housing LLP
K L Valeria
possession by Sep 2026 · K L Housing LLP
K M Enterprises
declared completion Dec 2020 · K M Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026