MahaRERA Property Intelligence · Mumbai Suburban
P51800003270 · Borivali · promoter Epitome Residency Private
| MahaRERA registration | P51800003270 |
| Registered on | 05 Aug 2017 |
| Promoter-declared completion | 30 Dec 2021 |
| Current status | Certificate Signed |
| Against today | about 55 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Epitome Residency Private is the promoter of record on 142 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+50.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Imperial Heights Wing C | 1 | G+50 | 30 Jun 2019 |
| Imperial Heights Wing D | 1 | G+50 | 30 Jun 2019 |
29 complaints are on the MahaRERA record for this project, with orders passed in 28. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000044398 | 03/05/2018 | MK_RADIUS vs RADIUS DEVELOPERS PVT LTD | order passed |
| CC006000000090150 | 15/07/2019 | MALIK AMIRBHAI CHARANIA vs WADHWA/RADIUS/EPITOME RESIDENCY PVT LTD | order passed |
| CC006000000001071 | 04/10/2017 | Mr. Sharan Bihari Lund / Mrs Vandana Sharan Lund vs Epitome Residency Private Limited | order passed |
| CC006000000001627 | 03/11/2017 | Sudhir Mahendra Joshi vs Epitome Residency Pvt Ltd | order passed |
| CC006000000044119 | 27/04/2018 | Mahesh Chandak vs Epitome Residency Pvt Ltd | order passed |
| CC006000000044204 | 20/04/2018 | Bhaskar Konati vs Epitome REsidency Private Limited | order passed |
| CC006000000054950 | 15/06/2018 | Bhuvanesh Shrivastava and Priyali Saxena vs Epitome Residency Pvt. Ltd. | order passed |
| CC006000000057670 | 14/01/2019 | Ajay Karan Oberoi vs Epitome Residency Pvt Ltd | order passed |
| CC006000000078533 | 18/03/2019 | Veenu VijayKumar Chawla vs Epitome Residency Private Limited | order passed |
| CC006000000089970 | 06/07/2019 | Vikas Pandey vs EPITOME RESIDENCY PRIVATE LIMITED | order passed |
| CC006000000181965 | 24/12/2019 | Chetan Solse vs Epitome Residency Private Limited | order passed |
| CC006000000110896 | 13/09/2019 | Maureen Motwane vs Epitome Residency Private Ltd | order passed |
| CC006000000110897 | 13/09/2019 | Harish Bhimani vs Epitome Residency Private Ltd | order passed |
| CC006000000209491 | 21/12/2021 | Dheeraj Jaggi vs Epitome Residency Private Limited | order passed |
| CC006000000209492 | 21/12/2021 | Dheeraj Jaggi vs Epitome Residency Private Limited | order passed |
| CC006000000141025 | 26/09/2019 | Sadiq Hussain Zahir Hussain Shaikh vs Vijay Associates (Wadhwa) Constructions Private Limited | order passed |
| CC006000000192230 | 22/01/2020 | Mrs Renuka Ramesh Bhatia vs M/s Wadhwa Group Holdings | order passed |
| CC006000000192262 | 26/02/2020 | Hemant Shukla & Charu Shukla vs EPITOME RESIDENCY PRIVATE LIMITED | order passed |
| CC006000000192323 | 19/02/2020 | JATIN LALITBHAI SHAH vs EPITOME RESIDENCY PVT LTD | order passed |
| CC006000000192512 | 08/02/2020 | Ashok Goyal vs Epitome Residency Pvt Ltd | order passed |
| CC006000000193081 | 20/03/2020 | Ajay Ram Modgil vs Epitome Residency Private Limited | order passed |
| CC006000000193082 | 08/04/2020 | Ajay Ram Modgil vs Epitome Residency Private Limited | order passed |
| CC006000000193254 | 16/06/2020 | Sylvester Henry Chaves vs Epitome Residency Private Limited | order passed |
| CC006000000196315 | 09/03/2021 | GAURAV RAMCHANDRA INGAVALE vs Epitome Residency Pvt. Ltd. | order passed |
| CC006000000199198 | 01/12/2021 | PRADEEP MUNNALAL SINGHAL vs (1) EPITOME RESIDENCY PVT LTD (2) SANJAY RAJKUMAR CHHABRIA (3) ANIL NANDLAL CHHABRIA | order passed |
| CC006000000220684 | 07/04/2022 | Chetan M Kamat vs Epitome Residency Pvt Ltd | order passed |
| CC006000000220912 | 29/04/2022 | Mona Sandeep Wazarkar vs Epitome Residency Private Limited | order passed |
| CC006000000221104 | 13/05/2022 | Zulfeequar Daulatkhan Sarguroh vs WADHWA GROUP HOLDINGS PVT. ;LTD & ORS. | pending / no order on file |
| CC006000000251585 | 23/06/2022 | Sushma Kaul vs Epitome Residency Private Limited | order passed |
The promoter has declared 8 court cases on this project to MahaRERA. 5 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Bombay High Court | 1393 | 2018 | Pending |
| Bombay High Court | 3714 | 2017 | Disposed Off |
| Maha Rera | CC006000000044204 | 2018 | Pending |
| Maha Rera | CC006000000044119 | 2018 | Disposed Off |
| City Civil Court At Dinsoshi | 200159 | 2017 | Pending |
| Bombay High Court | 97 | 2017 | Disposed Off |
| Maha Rera | CC006000000057670 | 2019 | Pending |
| Bombay High Court | 551 | 2019 | Pending |
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Dec 2021 | 29 Jun 2020 | We hereby submit that we have commenced and completed the RCC structure and internal walls of the entire Tower C comprising of 47 slabs. We are attaching a certificate of an Archit |
| 30 Dec 2021 | 30 Jun 2021 | A) Due to Covid 19 Pandemic and lock down in the country, the construction & related activities were stopped. B) Restrictions on movement of labour force and allowing only essenti |
Located at Borivali, Nalla and 13 MTR wide Road, Andheri, Mumbai Suburban, 400047. Per the filed land record, the plot is bounded to the north by Imperial Heights Tower A and B, to the south by Ankur Co op housing society, to the east by 12 MTR Wide internal Road and to the west by Nalla and 13 MTR wide Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Andheri MIDC / SEEPZ | 4 km |
| Chhatrapati Shivaji Int'l Airport | 7 km |
| Powai / Hiranandani business park | 8 km |
| Bandra Kurla Complex (BKC) | 10 km |
| Lower Parel / Worli business district | 17 km |
| Nariman Point / Fort | 25 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Imperial Heights Wing C and D?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026