Mumbai/Project record

MahaRERA · the public record

JIVDANI HEIGHTS

DONGARPADA VIRAR WEST · PRAKASH KASHINATH DESHMUKH

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000024737

Delivery and registration

When is the project declared for completion?

JIVDANI HEIGHTS is registered with MahaRERA as P99000024737 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000024737
Registered on02 Mar 2020
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JIVDANI HEIGHTS record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Prakash Kashinath Deshmukh is the promoter of record on 69 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

69projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for JIVDANI HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
JIVDANI HEIGHTS WING A AND B1G+431 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at DONGARPADA VIRAR WEST, OPP Z P SCHOOL HOLI AALI, Vasai, Palghar, 401303. Per the filed land record, the plot is bounded to the north by Z P SCHOOL AND DONGAR PADA GAOTHAN LAND, to the south by REMAINING PROPERTY OF SURVEY NO 235 HISSA 1 AND 4, to the east by SURVEY NO 235 HISSA NO 2 and to the west by ROAD AND DONGAR PADA GAOTHAN LAND. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~38 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ38 km
Powai / Hiranandani business park40 km
Chhatrapati Shivaji Int'l Airport42 km
Bandra Kurla Complex (BKC)45 km
Lower Parel / Worli business district52 km
Nariman Point / Fort60 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Virar West

Mayfair Virar Gardens Building NO 23, 24 And 25
possession by Sep 2026 · Mayfair Housing
Dattachhaya
possession by Nov 2026 · Jagdish Manohar Mhatre
Solaris Wing E-1 Hdil Layout
possession by Dec 2026 · Sunshine Developers
Star ERA
possession by Dec 2026 · Star Builders & Developers
Sugandhi Square
possession by Dec 2026 · R. N. Realty
Vitthal Haven
possession by Dec 2026 · Sushila Builders & Developers

Other RERA-registered projects in Palghar

Jivdani Heights
possession by Dec 2029 · Jivdani Developers
Jivdani Heights A AND B Wing
declared completion Dec 2024 · Rajendra Ramchandra Vane
Jivdani Home
possession by Dec 2027 · Vinay Harihar Singh
Jivdani Mata CO-Operative Housing Society LTD
possession by Dec 2027 · Kishore Gajanan Patil
Jivdani Mauli
possession by Dec 2026 · Kiran Ramesh Patil
Jivdani Plaza
declared completion May 2023 · Milind Shridhar Surve

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026