Mumbai/Project record

MahaRERA · the public record

JP GALAXY

Ambernath · JP CORP LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

201units filed as unsoldInventory · 16 September 2026
31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
306registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700013871

Delivery and registration

When is the project declared for completion?

JP GALAXY is registered with MahaRERA as P51700013871 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700013871
Registered on30 Oct 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for JP GALAXY record 33 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 33 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In JP GALAXY, ₹63.71 Cr of a declared ₹142.21 Cr estimated project cost is reported as incurred, about 44.8%, as at the last certified filing with MahaRERA.

44.8%

₹63.71 Cr

of ₹142.21 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In JP GALAXY, 105 of 306 homes filed with MahaRERA are recorded as sold or booked (61 with registered agreements and 44 booked), about 34%, and 201 remain available.

34%sold

105 of 306 homes

₹55.91 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹25.87 Cr (about 46%) is recorded as collected and ₹30.04 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 105 registered agreements, the effective carpet rate is ₹8,191/sqft, with eight in ten falling between ₹6,889 and ₹9,832 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 105 homes carry one, and 201 of the 306 are recorded unsold. Since we started watching this ledger, 18 homes have moved out of the unsold list, most recently on 18 July 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
SHOP 7488 sqftRs 7,749 a sq ft typical, over Rs 6,674 to Rs 9,64444 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In JP GALAXY, 174 of the 201 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 200 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24 and 306 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
ARCADIA1G+245-
EARTH1G+24117-
VENUS1G+24144-

Unit mix on the filing: 237 residential and 69 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2026We, JP Corp LLP, the Promoter of the real estate project “JP Galaxy” bearing MahaRERA Registration No. P51700013871, hereby submit this request seeking an extension of time for com

Location, Land & Connectivity

Located at Ambernath, Ambarnath, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by SR NO 63, to the south by ROAD, to the east by FOREST and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~30 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park30 km
Andheri MIDC / SEEPZ33 km
Chhatrapati Shivaji Int'l Airport35 km
Bandra Kurla Complex (BKC)35 km
Lower Parel / Worli business district43 km
Nariman Point / Fort48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters
Dalals Square
possession by Sep 2026 · Dalal Realty
GNP Galaxy Phase - III
possession by Sep 2026 · Roshni Enterprises
Meera Nanda Bliss
possession by Nov 2026 · Meera Homes LLP
Raj Residency
possession by Nov 2026 · Vijay Chahu Patil

Major developers building in Ambernath

Other RERA-registered projects in Thane

JP North Aviva
possession by Dec 2026 · JP Infra Realty Private Limited
JP North Estella
declared completion Dec 2021 · JP Infra Realty Private Limited
JP Symphony Bldg NO 5
declared completion Dec 2024 · Risali Developers
Juhi Elegance
possession by Dec 2030 · Juhi Habitat Pvt. Ltd.
Juhi Empressa
possession by Apr 2030 · Juhi Habitat Pvt. Ltd.
Junomoneta - Apollo
possession by Dec 2031 · Palika Infratech LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026