MahaRERA Property Intelligence · Thane

JP REGENCY PHASE 1

P51700013777 · AMBERNATH OLD VILLAGE · promoter Jp Developers

Certificate SignedDue 30 Jun 2021

Delivery & Registration

MahaRERA registrationP51700013777
Registered on25 Oct 2017
Promoter-declared completion30 Jun 2021
Current statusCertificate Signed
Against todayabout 61 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
WING A1G+1331 Dec 2020
WING B1G+1231 Dec 2020
WING C1G+1331 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202131 Dec 2021Due to Corona Pandemic and lockdown restrictions, our project was completely shut and no further work was possible. Also after ease of lockdown restrictions, Due to lower number of

Location, Land & Connectivity

Located at AMBERNATH OLD VILLAGE, 54/4A, 57/1, 57/2, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by S NO 131 H NO 131 8 1A 2K, to the south by S NO 57 H NO 2, to the east by S NO 57 H NO 2 and to the west by S NO 54. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~29 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park29 km
Andheri MIDC / SEEPZ33 km
Chhatrapati Shivaji Int'l Airport34 km
Bandra Kurla Complex (BKC)35 km
Lower Parel / Worli business district42 km
Nariman Point / Fort47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

JP Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by JP Developers

Other RERA-registered projects in Ambernath

24 High Bizbay
possession by Jul 2026 · Apex Infra
Shree Gajanan Enterprises Rukhmini CHS
possession by Jul 2026 · Shree Gajanan Enterprises Rukhmini CHS
Walekar Homes
possession by Aug 2026 · Walekar & Son's Developers
Patels Eirene
possession by Aug 2026 · Pramukh Developers
Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters

Major developers building in Ambernath

Other RERA-registered projects in Thane

JP Regency Phase 2
declared completion Feb 2023 · JP Developers
JP Symphony
declared completion Mar 2022 · Risali Developers
JP Symphony Bldg NO 5
declared completion Dec 2024 · Risali Developers
JP Synergy
declared completion Dec 2021 · Aashvi Developers
JP Synergy Phase 1 Building NO-2
declared completion Dec 2019 · Aashvi Developers
JSK Park
declared completion Dec 2022 · Shiv SAI Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026