Mumbai/Project record

MahaRERA · the public record

K.B.HEIGHTS

AIROLI · JAI GANESH GRUHNIRMAN PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

7units filed as unsoldInventory · 12 September 2026
31 Jan 2024declared completionMahaRERA registration · read 12 Jul 2026
42registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jan 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700021895

Delivery and registration

When is the project declared for completion?

K.B.HEIGHTS is registered with MahaRERA as P51700021895 and the promoter has declared completion for 31 Jan 2024.

31 Jan 2024

declared completion

32months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700021895
Registered on08 Aug 2019
Promoter-declared completion31 Jan 2024
Current statusCertificate Signed
Against todayabout 32 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for K.B.HEIGHTS record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Jai Ganesh Gruhnirman is the promoter of record on 13 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

13projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In K.B.HEIGHTS, 23 of 30 homes filed with MahaRERA are recorded as sold or booked, about 77%, and 7 remain available.

77%sold

23 of 30 homes

₹8.35 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹6.78 Cr (about 81%) is recorded as collected and ₹1.57 Cr as receivable. The project registers 42 homes in total, while this sold/unsold inventory filing covers 30 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 23 registered agreements, the effective carpet rate is ₹8,821/sqft, with eight in ten falling between ₹7,907 and ₹10,803 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1105469 sqft (43.58 sqm)₹33.34 Lakh
Floor 6602257 sqft (23.92 sqm)₹18.30 Lakh
Floor 6603448 sqft (41.59 sqm)₹31.81 Lakh
Floor 7702257 sqft (23.92 sqm)₹18.30 Lakh
Ground/Floor 03208 sqft (19.32 sqm)₹20.09 Lakh
Ground/Floor 05294 sqft (27.34 sqm)₹28.44 Lakh
Ground/Floor 06425 sqft (39.5 sqm)₹41.09 Lakh

The inventory filing also declares: 12 not for sale.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 23 homes carry one, and 7 of the 42 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
6425 sqftRs 38.00 lakh typical, over Rs 33.00 lakh to Rs 44.90 lakh7 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In K.B.HEIGHTS, 3 of the 7 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 6 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 42 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
K B HEIGHTS1G+74231 Aug 2022

Unit mix on the filing: 35 residential and 7 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jan 2024Application has been made for NOC to Sewage Department, Water Department & for Lift Function certificate. Occupancy Certificate is on hold due to this reasons. Necessary procedures

Location, Land & Connectivity

Located at AIROLI, SECTOR 1 VILLAGE AIROLI, Thane, Thane, 400708. Per the filed land record, the plot is bounded to the north by NINE METER WIDE ROAD, to the south by DESHMUKH CHAWL, to the east by SHRI GANESH APARTMENT and to the west by OPEN LAND. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ14 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district25 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Airoli

Alliaance Galaxy
possession by Oct 2026 · Aashutosh Enterprise
Bramharaj Orchid
possession by Dec 2026 · Bramharaj Developers
ONE Pyramid
possession by Dec 2026 · Pacific Properties
Surbhi Sangeeta Co-Op. Housing Society Ltd
possession by Dec 2026 · Kumar & Kumar Builders LLP
Delta Luxuria
possession by Apr 2027 · Shreenathji Organisers PVT LTD
Delta Icon
possession by Jul 2027 · Shreenathji Organisers PVT LTD

Other RERA-registered projects in Thane

K D Hermitage Building NO 1
possession by Dec 2026 · Kothari Creation
K. E. Zojwalla Commercial Center
possession by Dec 2026 · Johar Hasan Zojwalla
K.e.zojwalla Commercial Center
possession by Jun 2027 · Ayyub Chand Meo Khan
K K Renuka Residency A AND B Wing
declared completion Dec 2022 · Madhu Kachharam Achhra HUF
K K Residency
possession by Dec 2027 · Itnoa Construction Private Limited
K R Heights
declared completion Dec 2023 · Richi Rich Infrastructure

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026