MahaRERA Property Intelligence · Raigarh

KAMALJA

P52000017514 · ULWE · promoter Saivijay Builders And

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52000017514
Registered on23 Aug 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
KAMALJA1G+1331 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at ULWE, SECTOR 9, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by 15 MTRS WIDE ROAD, to the south by PLOT NO 154 AND 155, to the east by PLOT NO 157 and to the west by PLOT NO 159. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district20 km
Powai / Hiranandani business park20 km
Chhatrapati Shivaji Int'l Airport21 km
Nariman Point / Fort21 km
Andheri MIDC / SEEPZ23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Kamdhenu Aura
possession by Mar 2029 · Kamdhenu Enterprises
Kamla Avenue
declared completion Jul 2022 · Rohidas Laxman Mokal
Kanak Residency
declared completion Jun 2026 · Vivan Realtors
Kanakia Greenberg
declared completion Mar 2025 · Kanakia Spaces Realty PVT LTD
Kanakia Valley
possession by Dec 2030 · Kanakia Transparent Developers Private L
Kanha Heights
possession by Dec 2027 · Shree Krishna Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026