27 Feb 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

27 Feb 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000015158

Delivery and registration

When is the project declared for completion?

KANCHAN UNIVERCE BLDG NO.-9, C- TYPE UNIT NO.-01 is registered with MahaRERA as P99000015158 and the promoter has declared completion for 27 Feb 2024.

27 Feb 2024

declared completion

31months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000015158
Registered on02 Feb 2018
Promoter-declared completion27 Feb 2024
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KANCHAN UNIVERCE BLDG NO.-9, C- TYPE UNIT NO.-01 record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KANCHAN UNIVERCE BLDG NO.-9, C- TYPE UNIT NO.-01 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
KANCHAN UNIVERSE BLDG NO-9, C-TYPE1G+310 Jan 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered27 Feb 2024WE SEEK RENEWAL OF PROJECT REGISTRATION UNDER MAHARERA ON URGENT BASIS. AS PER MAHARERA CIRCULAR/NOTIFICATION/ORDER NO.21/2021 MAHARERA/SECY/FILE NO.27/157/2021, PROJECT EXTENS

Location, Land & Connectivity

Located at Mahim, Mahim, Thane, Thane, 401402. Per the filed land record, the plot is bounded to the north by RG, to the south by SURVEY NO-404, to the east by SCHEME BUILDING NO-10 and to the west by SURVEY NO-406. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~61 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ61 km
Powai / Hiranandani business park63 km
Chhatrapati Shivaji Int'l Airport65 km
Bandra Kurla Complex (BKC)68 km
Lower Parel / Worli business district74 km
Nariman Point / Fort82 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Sanmukh Sunshine
Not filing quarterly progress reports · possession by Oct 2026 · Sanmukh Realty LLP
Bafna Luxuria
possession by Dec 2026 · Shrushti Developers
Krishna Solitaire - 1
possession by Dec 2026 · Inspiration SG Infracon LLP
Krishna Solitaire - 2
possession by Dec 2026 · Inspiration SG Infracon LLP
Shakti Industrial Estate
Not filing quarterly progress reports · possession by Dec 2026 · Shakti Krupa Developers
Star Signature City-Star Emerald
possession by Dec 2026 · Star Builders & Developers

Other RERA-registered projects in Palghar

Kaneri Heights
possession by Sep 2026 · Shekhar Bhoir AND Others
Kanti Dhuri Sheraton
possession by Mar 2028 · Ghanshyam Infra
Kanti Vedanta
possession by Dec 2028 · Mahavir Infinity
Karari Heritage
possession by Dec 2030 · Karari Builders & Developers
Karrm Brahmaand Affordable Homes PVT LTD
possession by Dec 2026 · Karrm Brahmaand Affordable Homes Private
Kashi Arcade
declared completion Oct 2024 · Vedit Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.