Mumbai/Project record

MahaRERA · the public record

KASTURI HEIGHTS

BHAYANDAR EAST · ANNAPURNA REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700001116

Delivery and registration

When is the project declared for completion?

KASTURI HEIGHTS is registered with MahaRERA as P51700001116 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700001116
Registered on26 Jul 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KASTURI HEIGHTS record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Annapurna Realtors is the promoter of record on 17 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

17projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KASTURI HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+42.

BuildingWingsFloorsDeclared completion
KASTURI HEIGHTS1G+4231 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 20221. COVID-19 (Corona Virus) Pandemic has adversely affected the completion of our project. 2. Due to Nationwide lockdown from March 2020, many of our labourers had migrated to their
30 Jun 202230 Dec 20231. We have completed 100% work of the Project. 2. We are in the process of procuring the Occupancy Certificate. 3. We have also taken consent for extension from more than 51%

Location, Land & Connectivity

Located at BHAYANDAR EAST, 100 FEET GHODBUNDER ROAD, Thane, Thane, 401105. Per the filed land record, the plot is bounded to the north by ANAND RESIDENCY, to the south by OPEN PLOT COLLECTOR LAND, to the east by THIRTHRAJ RESIDENCY and to the west by RBK GLOBAL SCHOOL. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ19 km
Powai / Hiranandani business park21 km
Chhatrapati Shivaji Int'l Airport24 km
Bandra Kurla Complex (BKC)26 km
Lower Parel / Worli business district34 km
Nariman Point / Fort42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhayander East

Gayatri Elegance
possession by Dec 2026 · Gayatrikripa Developers Private Limited
Basera Heights
possession by Dec 2026 · Kamruddin Hasmullah Siddique
Durga Enclave
possession by Dec 2026 · Anmol Developers
Ranuja Ramdev C Type
possession by Dec 2026 · Ranuja Ramdev C Type
Surya Heritage A
possession by Dec 2026 · Arun Construction CO
The Pentagon
possession by Dec 2026 · Anjani Kumar Realty Private Limited

Other RERA-registered projects in Thane

Kasturi Heights
possession by Dec 2030 · Kastuti Developers
Kasturi Home Tower
possession by Dec 2026 · Shree Morya Associates
Kasturi Palaza
declared completion Jun 2026 · Arfa Construction
Kasturi VAN
possession by Dec 2029 · Gujarat Estate
Katarias
declared completion Mar 2024 · Sumit Developers
Katarias Shiv Shrishti
declared completion Dec 2025 · Shiv Sagar Developers AND Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026