MahaRERA Property Intelligence · Mumbai Suburban

Kaveri Krishna

P51700005237 · promoter Shree Shakti Developers

Certificate SignedDue 30 Sep 2018

Delivery & Registration

MahaRERA registrationP51700005237
Registered on11 Aug 2017
Promoter-declared completion30 Sep 2018
Current statusCertificate Signed
Against todayabout 94 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Shakti Developers is the promoter of record on 129 projects, of which 19 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
KAVERI1G+8-
KRISHNA1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 201830 Sep 2018Survey no 235 & 236/1 has two buildings planned, one building has 2 wings namely B-1 (kaveri) & B-2 (krishna) and another building namely "A" wing (unnamed). For both buildings, we

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 421601. Per the filed land record, the plot is bounded to the north by Pardi No 9 Gaothan Property, to the south by Survey No 125 Hissa 7 Pardi No 125 Hissa 7, to the east by Pardi No 11 Hissa 1 Pardi No 11 Hissa 2 and to the west by Pardi No 125 Hissa 5 Pardi No 10. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park15 km
Andheri MIDC / SEEPZ17 km
Chhatrapati Shivaji Int'l Airport20 km
Bandra Kurla Complex (BKC)22 km
Lower Parel / Worli business district30 km
Nariman Point / Fort38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Shakti Developers is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Shree Shakti Developers

Shree Shakti Developers
FlaggedThane
Shree Shakti Developers
FlaggedThane
Shree Shakti Developers
FlaggedThane

Other RERA-registered projects in Shahapur

Vaishnavi Dham Complex
possession by Jul 2026 · Vaishnavi Builders AND Developers
UMA Residency, Phase I
possession by Aug 2026 · Adarsh Infra Developers
Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
SAI Palace
possession by Oct 2026 · Vardhaman Developers
Sava Arcade
possession by Oct 2026 · Sava Developers

Major developers building in Shahapur

Other RERA-registered projects in Thane

Kavita Pearl
declared completion Oct 2019 · Kavita Infra
Kavita Residency
declared completion Oct 2022 · Kavita Buildcon LLP
Kavita Tower
possession by Nov 2029 · Kuber Construction Company
Kavya Grandeur
declared completion Dec 2022 · Jupiter Landscapes Pvt. Ltd.
Kavya Park
possession by Jun 2027 · Shree Construction Company
Kavya Residency
declared completion Dec 2021 · Kavya Mira Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026