Mumbai/Project record

MahaRERA · the public record

KAVYA GRANDEUR

THANE · JUPITER LANDSCAPES PVT. LTD.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700007431

Delivery and registration

When is the project declared for completion?

KAVYA GRANDEUR is registered with MahaRERA as P51700007431 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700007431
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KAVYA GRANDEUR record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Jupiter Landscapes is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KAVYA GRANDEUR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
KAVYA GRANDEUR1G+2130 Dec 2022

Legal and disputes

What disputes are disclosed?

10 complaints are on the MahaRERA record for KAVYA GRANDEUR, with orders passed in 10 of them.

10complaints

10with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000011082908/09/2019Haresh Desai vs Kavya Buildcon Pvt Ltdorder passed
CC00600000019569119/01/2021HT Media Ltd. vs Kavya Buildcon Private Limitedorder passed
CC00600000019569419/01/2021HT Media Ltd. vs Kavya Buildcon Private Limitedorder passed
CC00600000019482305/11/2020Alghu Yadav vs M/s Anil Sunder & Co.order passed
CC00600000047993304/04/2024Prathamesh Sunil Tipnis vs Jupiter Landscape Pvt Ltd Company, Through its Director Mr Ambish Shahorder passed
CC00600000040856103/01/2024REKHA SHAH vs M/S KAVYA BUILDCON PVTLTDorder passed
CC00600000040856203/01/2024RESHMA SHAH vs M/S KAVYA BUILDCON PVT LTDorder passed
CC00600000040857310/01/2024MONA MEHTA vs M/S KAVYABUILDCON PVT LTDorder passed
CC00600000040859510/01/2024ROOSHABH SANGHVI vs KAVYA BUILDCON PVT- LTDorder passed
CC00600000059116512/07/2024HT MEDIA LIMITED vs KAVYA BUILDCON PRIVATE LIMITEDorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court5852015Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS

Location, Land & Connectivity

Located at THANE, THANE, Mumbai City, Mumbai City, 400607. Per the filed land record, the plot is bounded to the north by 19 15 55 51 N 72 57 46 54 E, to the south by 19 15 52 24 N 72 57 45 70 E, to the east by 19 15 53 85 N 72 57 47 44 E and to the west by 19 15 53 80 N 72 57 43 79 E. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ17 km
Chhatrapati Shivaji Int'l Airport21 km
Bandra Kurla Complex (BKC)23 km
Lower Parel / Worli business district32 km
Nariman Point / Fort39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kolshet

Godrej Exquisite
possession by Sep 2026 · Godrej Macbricks Private Limited
Lodha Crown Kolshet-Tower 1
possession by Sep 2026 · Lodha Developers Limited
Odysseus
possession by Sep 2026 · Sagar Enterprise
Unique Vistas Mhada Building NO. 1,2,3
possession by Sep 2026 · Madhu Harshad Doshi
Unique Vistas Mhada Buildingno. 4 5 6 7
possession by Sep 2026 · Madhu Harshad Doshi
Daffodil
possession by Dec 2026 · Shree Tirupati Greenfield Developers

Major developers building in Kolshet

Other RERA-registered projects in Thane

Kavya Park
possession by Jun 2027 · Shree Construction Company
KD House
declared completion Mar 2024 · Komplete Supply Chain Solutions PVT LTD
Kendale Emeralds
declared completion Oct 2024 · Kendale Developers
Kendale Emeralds
possession by Sep 2026 · Kendale Developers
Kerala Village Phase-2
possession by Mar 2027 · John Mathew
Kesari Park
declared completion Jan 2025 · Vijaya Construction

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026