MahaRERA Property Intelligence · Thane

KENDALE EMERALDS

P51700023217 · JADHAV NAGAR · promoter Kendale Developers

Certificate SignedDue 30 Sep 2026

Delivery & Registration

MahaRERA registrationP51700023217
Registered on06 Dec 2019
Promoter-declared completion30 Sep 2026
Current statusCertificate Signed
Against today2 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kendale Developers is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~85.8% of the estimated project cost incurred as of the last certificate (₹16.46 Cr spent against a ₹19.18 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 96 homes filed with MahaRERA, 73 are sold/booked (70 with registered agreements + 3 booked) and 23 remain available (~76% sold) — selling steadily. Buyers have committed ₹24.59 Cr in agreement value so far. Of that, ₹19.66 Cr (~80%) is already collected, ₹4.91 Cr receivable — a read on how far along these sales really are. Note: the project registers 148 homes in total, but this sold/unsold inventory filing covers only 96 of them — the other 52 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 73 registered agreements, the effective carpet rate is ₹6,816/sqft (typical range ₹6,236–₹7,430) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1102394 sqft (36.58 sqm)₹14.58 Lakh
Floor 1102416 sqft (38.66 sqm)₹15.70 Lakh
Floor 1104561 sqft (52.1 sqm)₹21.15 Lakh
Floor 1104510 sqft (47.37 sqm)₹42.51 Lakh
Floor 1105265 sqft (24.62 sqm)₹10.00 Lakh
Floor 101006389 sqft (36.18 sqm)₹28.01 Lakh
Floor 2201413 sqft (38.38 sqm)₹15.58 Lakh
Floor 2205265 sqft (24.62 sqm)₹17.43 Lakh
Floor 3303553 sqft (51.38 sqm)₹38.04 Lakh
Floor 4405509 sqft (47.32 sqm)₹35.51 Lakh
Floor 4405265 sqft (24.62 sqm)₹10.00 Lakh
Floor 5502394 sqft (36.58 sqm)₹14.85 Lakh
Floor 5502416 sqft (38.66 sqm)₹15.70 Lakh
Floor 5503509 sqft (47.3 sqm)₹19.20 Lakh
Floor 5505265 sqft (24.62 sqm)₹10.00 Lakh
Floor 7702394 sqft (36.58 sqm)₹28.88 Lakh
Ground/Floor 01183 sqft (17.02 sqm)₹9.50 Lakh
Ground/Floor 02170 sqft (15.81 sqm)₹8.82 Lakh
Ground/Floor 05205 sqft (19.07 sqm)₹10.64 Lakh
Ground/Floor 06192 sqft (17.87 sqm)₹9.97 Lakh
Ground/Floor 07192 sqft (17.87 sqm)₹9.97 Lakh
Ground/Floor 08202 sqft (18.74 sqm)₹10.46 Lakh
Ground/Floor 09355 sqft (33 sqm)₹18.41 Lakh

⚠ The inventory filing also declares: 52 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11 and 148 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING NO 3 WING D1G+1149-
BUILDING NO 4 WING E1G+631-
BUILDING NO 5 WING F1G+1168-

Unit mix on the filing: 133 residential and 15 non-residential (shops/offices).

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1260359710/06/2026Ankit Ramchandra Kharwade vs Kendale Developerspending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Oct 202530 Apr 2026Due to COVID 19 our construction progress got constantly affected and has continuously and regularly been delayed since then, thereby resulting into an overall delay in project exe
30 Oct 202530 Sep 2026Sir, we have substantially completed our project and the work of making application for OC i.e. Occupancy Certificate with the Municipal Authorities is on going and it being an adm

Location, Land & Connectivity

Located at JADHAV NAGAR , VILLAGE BELAVLI KATRAP ROAD , Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by S NO 70 71, to the south by S NO 69, to the east by DP ROAD and to the west by VILLAGE KATRAP. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Kendale Emeralds Phase III
possession by Dec 2026 · Kendale Developers
Kerala Village
declared completion Mar 2025 · John Mathew
Kerala Village Phase-2
possession by Mar 2027 · John Mathew
Kesari Park
declared completion Jan 2025 · Vijaya Construction
Keshar Aagan Cooperative Housing Society
possession by Sep 2026 · Gagan Homes
Keshav Height Building C
declared completion Jun 2024 · Nandkumar Balkrishna Salvi

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026