MahaRERA Property Intelligence · Thane

KESARI PARK

P51700019272 · SHAHAPUR · promoter Vijaya Construction

Certificate SignedDue 15 Jan 2025

Delivery & Registration

MahaRERA registrationP51700019272
Registered on15 Jan 2019
Promoter-declared completion15 Jan 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vijaya Construction is the promoter of record on 39 projects, of which 8 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
KESARI PARK1G+515 Jan 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SHAHAPUR, INTERNAL 9.00 METER WIDE ROAD, Bhiwandi, Thane, 421601. Per the filed land record, the plot is bounded to the north by EXISTING BUNGALOW, to the south by EXISTING RESIDENTIAL BUILDING, to the east by OPEN PLOT and to the west by MAIN ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park34 km
Andheri MIDC / SEEPZ37 km
Chhatrapati Shivaji Int'l Airport40 km
Bandra Kurla Complex (BKC)41 km
Lower Parel / Worli business district48 km
Nariman Point / Fort54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shahapur

Vaishnavi Dham Complex
possession by Jul 2026 · Vaishnavi Builders AND Developers
UMA Residency, Phase I
possession by Aug 2026 · Adarsh Infra Developers
Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
SAI Palace
possession by Oct 2026 · Vardhaman Developers
Sava Arcade
possession by Oct 2026 · Sava Developers

Major developers building in Shahapur

Other RERA-registered projects in Thane

Keshar Aagan Cooperative Housing Society
possession by Sep 2026 · Gagan Homes
Keshav Height Building C
declared completion Jun 2024 · Nandkumar Balkrishna Salvi
Keshav Kunj IV
declared completion Jul 2018 · Asha Developers
Ketan CO-Operative Housing Society Limited
declared completion Jul 2025 · Nextera Builders AND Developers
Keystone
possession by Dec 2030 · One Eleven Lifesarea LLP
Keystone Classic
declared completion Apr 2022 · Keystone Classic

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026