MahaRERA Property Intelligence · Thane

KRISHNA SUDAMA RESIDENCY

P51700021284 · KULGAON · promoter Sai Homes

Certificate SignedDue 30 Sep 2026

Delivery & Registration

MahaRERA registrationP51700021284
Registered on18 Jun 2019
Promoter-declared completion30 Sep 2026
Current statusCertificate Signed
Against today2 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~100.0% of the estimated project cost incurred as of the last certificate (₹21.06 Cr spent against a ₹21.06 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 123 homes filed with MahaRERA, 91 are sold/booked and 32 remain available (~74% sold) — selling steadily. Buyers have committed ₹18.73 Cr in agreement value so far. Of that, ₹18.43 Cr (~98%) is already collected, ₹30.34 Lakh receivable — a read on how far along these sales really are. Note: the project registers 175 homes in total, but this sold/unsold inventory filing covers only 123 of them — the other 52 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 91 registered agreements, the effective carpet rate is ₹6,354/sqft (typical range ₹5,046–₹7,237) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101264 sqft (24.51 sqm)₹16.51 Lakh
Floor 1103260 sqft (24.14 sqm)₹16.27 Lakh
Floor 1109263 sqft (24.46 sqm)₹16.48 Lakh
Floor 1111452 sqft (42.02 sqm)₹28.89 Lakh
Floor 2203260 sqft (24.14 sqm)₹16.27 Lakh
Floor 2212352 sqft (32.72 sqm)₹22.38 Lakh
Floor 3301264 sqft (24.51 sqm)₹16.51 Lakh
Floor 4401264 sqft (24.51 sqm)₹16.51 Lakh
Floor 4403260 sqft (24.14 sqm)₹16.27 Lakh
Floor 4405458 sqft (42.52 sqm)₹29.18 Lakh
Floor 4406264 sqft (24.51 sqm)₹16.51 Lakh
Floor 4408352 sqft (32.72 sqm)₹22.37 Lakh
Floor 4409263 sqft (24.46 sqm)₹16.48 Lakh
Floor 5501264 sqft (24.51 sqm)₹17.34 Lakh
Floor 5505458 sqft (42.52 sqm)₹30.64 Lakh
Floor 5506264 sqft (24.51 sqm)₹17.34 Lakh
Floor 5509263 sqft (24.46 sqm)₹17.30 Lakh
Floor 5511452 sqft (42.02 sqm)₹30.34 Lakh
Floor 6601264 sqft (24.51 sqm)₹17.34 Lakh
Floor 6603260 sqft (24.14 sqm)₹17.09 Lakh
Floor 6605458 sqft (42.52 sqm)₹30.64 Lakh
Floor 6609263 sqft (24.46 sqm)₹17.30 Lakh
Floor 6611452 sqft (42.02 sqm)₹30.34 Lakh
Floor 7701264 sqft (24.51 sqm)₹17.34 Lakh
Floor 7705458 sqft (42.52 sqm)₹30.64 Lakh
Floor 7706264 sqft (24.51 sqm)₹17.34 Lakh
Floor 7707352 sqft (32.72 sqm)₹23.48 Lakh
Floor 7708352 sqft (32.72 sqm)₹23.49 Lakh
Floor 7709263 sqft (24.46 sqm)₹17.30 Lakh
Floor 7710350 sqft (32.48 sqm)₹23.34 Lakh
Floor 7711452 sqft (42.02 sqm)₹30.34 Lakh
Floor 7712352 sqft (32.72 sqm)₹23.50 Lakh

⚠ The inventory filing also declares: 52 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 175 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
KRISHNA SUDAMA RESIDENCY - A WING1G+546-
KRISHNA SUDAMA RESIDENCY - B WING1G+884-
KRISHNA SUDAMA RESIDENCY - C WING1G+545-

Unit mix on the filing: 175 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202430 Sep 2025There was 3 wings in the Project viz. A, B and C. However, A wing is completed and its OC is received, whereas C wing is also completed. Whereas, B Wing Construction started in 202
30 Sep 202430 Sep 2026We respectfully request an extension, as our project has lapsed and the project work has not yet been completed.

Location, Land & Connectivity

Located at KULGAON, BELAVALI GAON, Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by LAND BEARING Sr No 7A p, to the south by LAND BEARING Sr No 7A p, to the east by LAND BEARING Sr No 7A p and to the west by LAND BEARING Sr No 5 p. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SAI Homes is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by SAI Homes

SAI Homes
Past its declared completion datePalghar

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Krishna Trident
possession by Jun 2030 · Sonawane Infrastructure Private Limited
Krishna Vansh
possession by Dec 2028 · Chaitanya Developers
Krishna Vihar
declared completion Jun 2018 · Krishna Space
Krishna Vihar Co-Operative Housing Society Limited
declared completion Dec 2021 · BAL Ganapati Laabh Developers
Krishna Villa
declared completion Dec 2023 · Royal Builders & Developers
Krishna Wing C
possession by Dec 2029 · K Rudraksh Realtors LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026