MahaRERA Property Intelligence · Thane

BALKRUSHNA CO-OP HOUSING SOCIETY LTD

P51700066544 · Village - Katrap, Taluka - Ambernath, Badlapur · promoter Sai Homes

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51700066544
Registered on11 Jun 2024
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~89.7% of the estimated project cost incurred as of the last certificate (₹2.81 Cr spent against a ₹3.14 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 12 homes filed with MahaRERA, 0 are sold/booked and 12 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Note: the project registers 29 homes in total, but this sold/unsold inventory filing covers only 12 of them — the other 17 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1102520 sqft (48.31 sqm)₹24.59 Lakh
Floor 1104458 sqft (42.52 sqm)₹21.64 Lakh
Floor 2202520 sqft (48.31 sqm)₹24.59 Lakh
Floor 3302520 sqft (48.31 sqm)₹24.59 Lakh
Floor 4401309 sqft (28.71 sqm)₹14.61 Lakh
Floor 4402520 sqft (48.31 sqm)₹24.59 Lakh
Floor 4403480 sqft (44.63 sqm)₹22.72 Lakh
Floor 5503480 sqft (44.63 sqm)₹22.72 Lakh
Floor 6602520 sqft (48.31 sqm)₹24.59 Lakh
Floor 7701309 sqft (28.71 sqm)₹14.61 Lakh
Floor 7702520 sqft (48.31 sqm)₹24.59 Lakh
Floor 7704458 sqft (42.52 sqm)₹21.64 Lakh

⚠ The inventory filing also declares: 17 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 29 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BALKRUSHNA CO-OP HOUSING SOCIETY LTD1G+729-

Unit mix on the filing: 28 residential and 1 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Village - Katrap, Taluka - Ambernath, Badlapur, Survey No. 30, Hissa No. 1/2 and Survey No.30, Hissa No. 1/3, Plot No.5,, Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by Gite Chawl, to the south by Road, to the east by Vidhat Chawl and to the west by Om Shubh Aashish Co Op Soc Ltd. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~35 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park35 km
Andheri MIDC / SEEPZ38 km
Chhatrapati Shivaji Int'l Airport39 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district46 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SAI Homes is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by SAI Homes

SAI Homes
Past its declared completion datePalghar

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Ballaleshwar
possession by Mar 2030 · Not Available
Ballaleshwar Galaxy
possession by Dec 2030 · Ballaleshwar Builders
Balram Complex
declared completion Jun 2026 · Universal Builders
Bama Kathod Heights
declared completion Mar 2024 · Vastu SAI Builders & Developers
Bama Patil Shopping Centre
declared completion Oct 2022 · Nivesh Enterprises
Bamubai Sadan
declared completion Oct 2021 · Samarth Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026