Mumbai/Project record

MahaRERA · the public record

KELJAI RESIDENCY

Raigarh · MATOSHRI BUILDER AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jan 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000010717

Delivery and registration

When is the project declared for completion?

KELJAI RESIDENCY is registered with MahaRERA as P52000010717 and the promoter has declared completion for 30 Jan 2026.

30 Jan 2026

declared completion

8months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000010717
Registered on31 Aug 2017
Promoter-declared completion30 Jan 2026
Current statusCertificate Signed
Against todayabout 8 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KELJAI RESIDENCY record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Matoshri Builder is the promoter of record on 16 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

16projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KELJAI RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
A WING1G+330 Jul 2022
B WING1G+330 Jul 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jul 2025As per the details mentioned at the time of registration of the project at the Maharera Website we have mentioned 31.01.2020 as the project completion date. However, we could not c

Location, Land & Connectivity

Located at Mangaon, Raigarh, 402104. Per the filed land record, the plot is bounded to the north by DALIBHAG AND FOREST, to the south by FOREST, to the east by FOREST and to the west by PLOT NO 237 AND 238. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~95 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort88 km
Lower Parel / Worli business district95 km
Bandra Kurla Complex (BKC)100 km
Chhatrapati Shivaji Int'l Airport102 km
Powai / Hiranandani business park104 km
Andheri MIDC / SEEPZ106 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mangaon

Chinmay Plaza
possession by Dec 2026 · Atmaram Narayan Shinde
Jazzworld
Not filing quarterly progress reports · possession by Dec 2026 · Jazzworld
Vishwa Apartments
possession by Dec 2026 · Ratnmala Ramesh Khanvilkar
Rukmini Heights
possession by Aug 2027 · RJM Constructions & Developers LLP
Riviera
Not filing quarterly progress reports · possession by Sep 2027 · Jairam Nandkishor Bhasin
Gurudev Apartment
possession by Dec 2027 · Rajesh Samarth Prabhu

Other RERA-registered projects in Raigarh

Kenisha Holiday Homes Cluster C-D
declared completion Jun 2025 · Kunal Avinash Kumthekar
Kenisha Holiday Homes Cluster H AND I
declared completion Dec 2020 · Kunal Avinash Kumthekar
Kenisha Holiday Homes - Cluster N
declared completion Dec 2020 · Kunal Avinash Kumthekar
Kenisha Holiday Homes - Cluster O
declared completion Dec 2021 · Kunal Avinash Kumthekar
Kenisha Resort Residences
possession by Dec 2026 · Kpin Real Estate Ventures
Kenisha Resort Residences - Cluster R1 TO R13 AND S1A TO S2B
possession by Dec 2026 · Kpin Real Estate Ventures

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026